on 12-14-2007 9:12 AM
Hi Gurus,
Where can i cofigure Service material(LEIH) to activity types in CS?
Quick help will be appreciated.
Regards,
Vikas
dear vikas
Customer Service (CS)
Contents
Customer Service (CS)..................................................................................8
Overview...................................................................................................................................9
Customer Service (CS) in IDES.............................................................................................10
Introduction........................................................................................................................11
Organization.......................................................................................................................12
Characteristic Values and Special Features.......................................................................14
Note for IDES Processes in the Customer Service Area....................................................18
Service Processing................................................................................................................19
Selling a Serialized Product and Creating an Equipment Master Record........................20
Data Used During This Process..........................................................................................21
Creating a Sales Order for a Serialized Product.................................................................22
Creating a Delivery..............................................................................................................23
Creating a Billing Document................................................................................................25
Checking the Sales Document Flow (Optional)..................................................................26
Creating the Equipment Data..............................................................................................27
Related IDES Processes.....................................................................................................29
Service Management - Spare Part Delivery.........................................................................30
Data Used During This Process..........................................................................................31
Creating a Service Notification and a Spare Parts Order...................................................32
Creating a Spare Parts Order.............................................................................................34
Creating the Billing Document............................................................................................35
Performing a Service Order and Billing...............................................................................36
Additional Process Information...........................................................................................38
Data Used During This Process..........................................................................................41
Creating the Initial Situation................................................................................................42
Entering a Problem Notification and Creating a Service Order..........................................43
Processing a Service Order................................................................................................45
Confirming a Service Order.................................................................................................47
Creating a Billing Request (Resource-Related Billing).......................................................50
Creating a Billing Document................................................................................................52
Settling and Completing the Service Order.........................................................................53
Displaying Line Items in Profitability Analysis.....................................................................55
Displaying a CS Report in Profitability Analysis..................................................................57
Returns and Repair Processing............................................................................................59
Additional Process Information...........................................................................................60
Data used during this Process............................................................................................63
Activating the QM Check.....................................................................................................64
Creating the Service Notification and the Repair Request.................................................66
Posting the Goods Receipt of a Piece of Equipment to be Repaired.................................68
Processing the Technical Check.........................................................................................70
Displaying the Repair Request and the Service Order.......................................................71
Editing the Service Order....................................................................................................72
Processing and confirming the Service Order....................................................................73
Technically Completing the Service Order..........................................................................76
Delivering the Repaired Piece of Equipment......................................................................78
Creating the Billing Request................................................................................................79
Invoicing the Repair Request..............................................................................................80
4 April 2001
SAP AG Customer Service (CS)
Settling and Completing the Service Order.........................................................................81
Analyzing the Result of the Repair request.........................................................................83
Deactivating the QM Check................................................................................................84
Creating a Service Order from a Sales Order......................................................................85
Additional Process Information...........................................................................................86
Data Used During This Process..........................................................................................88
Entering a Customer Notification and Creating a Service Order........................................90
Setting an Service Order to.................................................................................................93
Processing the Service Order.............................................................................................95
Settling the Service Order...................................................................................................98
Invoicing the Sales Order....................................................................................................99
Analyzing the Cost Report in the Sales Order..................................................................100
Settling the Sales Order....................................................................................................101
Analyzing Line Items in the Financial Statement..............................................................102
Processing Telephone Calls in a Call Center....................................................................104
Data Used During This Process........................................................................................105
Preparations: Assigning the CIC Profile............................................................................106
Preparation: Defining the Work Center.............................................................................108
Processing a Customer Call (Variant A)...........................................................................109
Processing a Customer Call (Variant B)...........................................................................112
Service Contracts.................................................................................................................114
Processing Service Contracts with Periodic Billing.........................................................115
Data Used During This Process........................................................................................116
Creating and Delivering Sales Orders..............................................................................117
Creating the Equipment Master Record............................................................................120
Creating Service Contracts for Maintenance of Customer Equipment.............................122
Maintaining Price Agreements in the Service Contract....................................................123
Service Processing and Resource-Related Billing (optional)...........................................124
Performing Periodic Billing Document..............................................................................125
Settlement of Service Contracts.......................................................................................127
Creating Service Contracts (Nonconfigurable).................................................................129
Creating Service Contracts with a Configurable Service Package...................................131
Creating Service Contracts with a Preconfigured Service Package.................................133
Displaying Line Items in Profitability Analysis...................................................................135
Displaying a CS Report in Profitability Analysis................................................................137
Service Processing and Resource-Related Billing with a Service Contract..................139
Data Used During This Process........................................................................................140
Creating a Service Order from a Notification....................................................................141
Assigning Components and Releasing a Service Order...................................................144
Posting Goods Issues for a Service Order........................................................................145
Confirming a Service Order...............................................................................................146
Creating a Billing Request.................................................................................................147
Creating a Billing Document from a Billing Request.........................................................149
Settling the Costs of the Service Order to the Service Contract.......................................150
Spare Parts Delivery with a Service Contract...................................................................153
Additional Process Information.........................................................................................154
Data Used During This Process........................................................................................155
Creating a Service Notification and a Spare Parts Order.................................................156
Creating a Spare Parts Order...........................................................................................158
Creating the Billing Document..........................................................................................159
Controlling...........................................................................................................................160
April 2001 5
Customer Service (CS) SAP AG
Controlling for Services.......................................................................................................162
Additional Process Information.........................................................................................164
Data Used During This Process........................................................................................165
Displaying a CS Report in Profitability Analysis................................................................166
Displaying Line Items........................................................................................................168
Executing an Existing Report in Profitability Analysis and Getting to Know Reporting Functions.....................................................................................................................169
Additional Process Information...............................................................................170
Data Used During This Process.............................................................................171
Setting Up Parameters in Your User Profile...........................................................172
Selecting a Report in CO-PA..................................................................................173
Drilling Down to the Lowest Level (Including Line Item Detail)..............................175
Line Item Analysis (Including Integration with MM and SD)...................................179
Report-Report Interface..........................................................................................181
Displaying Attributes...............................................................................................182
Hit Lists...................................................................................................................183
Changing the Report Currency...............................................................................184
Displaying and Creating Exceptions.......................................................................185
Workflow in Customer Service...........................................................................................187
Workflow - Service Management........................................................................................188
Additional Process Information.........................................................................................189
Data Used During This Process........................................................................................190
Logging the Service Notification.......................................................................................191
Processing and Completing the Service Notification........................................................192
6 April 2001
SAP AG Customer Service (CS)
April 2001 7
Customer Service (CS) SAP AG
Customer Service (CS)
Customer Service (CS)
Overview
Service Processing
Selling a Serialized Product and Creating an Equipment Master Record
Service Management - Spare Part Delivery
Performing a Service Order and Billing
Creating a Service Order from a Sales Order
Processing Telephone Calls in a Call Center
Service Contracts
Processing Service Contracts with Periodic Billing
Service Processing and Resource-Related Billing with a Service Contract
Spare Parts Delivery with a Service Contract
Controlling
Workflow in Customer Service
8 April 2001
SAP AG Customer Service (CS)
Overview
Overview
April 2001 9
Customer Service (CS) SAP AG
Customer Service (CS) in IDES
Customer Service (CS) in IDES
The following documentation displays the organization of the Customer Service in IDES as well as the embedding of this service organization into the complete IDES enterprise. Above that, you will get an overview on the characteristics and specifications of the Customer Service module within IDES.
Characteristic Values and Special Features
Note for IDES Processes in the Customer Service Area
10 April 2001
SAP AG Customer Service (CS)
Introduction
Introduction
The IDES AG produces PC workstations for use in commercial or technical areas. The enterprise offers services for these products (installation, maintenance, repair). For some customers, the service agreements are determined via service contracts. Other customers, however, order services individually. The service measures are carried out either in the IDES service plant or at the customer location.
April 2001 11
Customer Service (CS) SAP AG
Organization
Organization
Planning Plant
The workstations are produced in the Dresden plant (1200) of the IDES AG (production plant). This plant is responsible for the planning and preparation of service measures (maintenance planning plant). The service measures are also executed in plant 1200.
Plant
Description
1200
Dresden
Work Center
Service technicians are collected into service groups using work places.
Work center
Description
Assigned Technician (personnel number)
PC-SERV
TS technician north (DE)
1522, 1523,1525, 1528, 1529
PC-SERVS
TS technician south (DE)
1504, 1505, 1500
PC-REP
Repair center
1955, 1956
PC-HELP
Help desk
1957, 1958
Planner Groups
There are three planner groups in the service plant that are responsible for materials planning for the work centers.
Planner group
Description
200
Service north
201
Service south
202
Repair service
Sales Organization in the Service Area
The sale of services and spare parts is handled by sales organization 1000. All sales activities in the service area are represented in this sales organization through an individual distribution channel. Sales in IDES occur across divisions through division 00. The following table lists the combinations of sales organization, distribution channel, and division that represent the sales area. This is used to enter all contracts, replacement part orders and other sales orders in the service area.
Organizational Unit
Key
Description
Sales organization
1000
Germany
Distribution channel
14
Service
Division
00
Cross-divisional 12 April 2001
SAP AG Customer Service (CS)
Organization
Integration with Financial Accounting
Service plant 1200 is assigned to company code IDES AG. Within this company code, the service represents its own business area. The service objects are assigned to this company code and business area. This assignment is transferred to a service order for this object. For service contracts, replacement part orders, and other sales orders, business area 8000 is derived from the sales area 1000/14/00.
Organizational Unit
Key
Description
Company code
1000
IDES AG
Business area
8000
External service
Integration with Controlling
Company code 1000 belongs to controlling area 1000 (Europe). From the Profitability Analysis perspective, this controlling area belongs to operating concern IDEA.
Organizational Unit
Key
Description
Controlling area
1000
CO Europe
Operating concern
IDEA
Operating concern IDES global
Integration with Materials Management
From the Materials Management perspective, all materials used for service measures are administered in plant 1200. Replacement parts and external services are procured via sales organization 1000.
Organizational Unit
Key
Description
Plant
1200
Dresden
Warehouse
0001;
1500 to 1507
Material storage;
Service vehicles 1 to 8
Purch. organization
1000
IDES Germany
April 2001 13
Customer Service (CS) SAP AG
Characteristic Values and Special Features
Characteristic Values and Special Features
Service Customer
IDES provides services for external customers. Long-term contracts exist for specific customers to process the service agreements.
Customer number
Name
Service contracts
1032
Institute for Environmental Studies
Yes
1034
ERL Freiburg
Yes
1171
Hitech AG
No
1172
CBD Computer Based Design
Yes
1177
Computer Competence Center AG
No
2141
Jaspers Computer
Yes
Service Objects
Equipment
IDES uses equipment as technical reference objects for services. An equipment master record exists for each workstation delivered to a customer. This means that each work station is an individual, physical object, which is viewed individually from the service perspective. The equipment master record also has serialization data (a unique combination of material number and serial number). This ensures that the equipment is also recorded for stock purposes as a serialized material.
Functional Locations
The equipment delivered to the customer is included in a functional location. The functional locations are used to organize the customers company structure according to functional and spatial viewpoints. Assuming that a hierarchical structure exists, the following list shows the highest level of the relevant location hierarchy.
Functional Locations
Description
1171
Hitech
1172
CBD Computer Based Design
1177
Computer Competence Center AG
1032
Institute for Environmental Studies
1034
ERL Freiburg
2141
Jaspers Computer
14 April 2001
SAP AG Customer Service (CS)
Characteristic Values and Special Features
Bills of Materials
The BOM of this material is used to describe the structure of the service object. This material BOM is indirectly assigned to each equipment through the construction type entered in the equipment master record. The BOM is also used to enter components and spare parts in Service Management.
The following list describes the BOM of material R-1001:
Material
Description
R-1001
Maxitec R-3100 Personal Computer
Component
Description
R-1111
Main circuit board 3100
R-1120
Cable 220/235 V with safety plug
R-1130
Keyboard, English international
R-1140
PAQ screen, 17, color
R-1150
Floppy disk drive, 3.5, HD
R-1160
Hard disk, 4.3 GB
R-1170
Slimline PC casing
Service Products
The services provided by IDES are described as service products using a product master record. In those cases in which the characteristic attributes of the given service have varying characteristics, the services are offered as either configurable or pre-configured products.
The following list shows the material numbers of the service products used in the IDES services:
service product
Description
Comment
HOTLINE_SERVICE
Hotline service
Configurable
HOTLINE_SERVICE_A
Hotline service package A (Mo-Fr/3h)
Pre-configured
HOTLINE_SERVICE_B
Hotline service package B (24h/3h)
Pre-configured
PC_SERVICE_CONF
PC Service
Configurable
PC_SERVICE_CONF
PC Service plus
Pre-configured
REPAIR_SERVICE
Desktop repair service
INSPECTION_SERVICE
Inspection service
Configurable
SM-PCREP
PC repair
SM-NETINST
Network installation
Configurable
April 2001 15
Customer Service (CS) SAP AG
Characteristic Values and Special Features
Service Contracts
IDES contains all the service contracts listed in the table below. The table lists the customer number and the characteristic attributes of each contract. The technical reference object of the contracts is the functional location. Provided that a location hierarchy exists, the highest level of this hierarchy is the reference object. The contract therefore comprises all equipment included in a functional location of the customer.
Document number
Customer
Characteristic attribute
40000073
1032
Configurable service product
Transfer from response profile and service profile to service notifications
Variant conditions
Price agreement in the form of a percentage discount for individual spare parts
Reference object = functional location 1032
40000074
1034
Configurable service product
Transfer from response profile and service profile to service notifications
Variant conditions
Price agreement in the form of a percentage discount for individual spare parts
Reference object = functional location 1034
40000075
1172
Pre-configured service product
Transfer from response profile and service profile to service notifications
Price agreement in the form of a percentage discount for the material group spare parts and for individual spare parts; Condition exclusion for transfer to spare parts orders or for resource-related billing
Reference object = functional location 1172
40000076
2141
Simple service product
Price agreement in the form of a 100 % discount for the material group spare parts
Reference object = functional location 2141
16 April 2001
SAP AG Customer Service (CS)
Characteristic Values and Special Features
Periodic Billing and Settlement
The service contracts available in IDES are billed and settled monthly by job processing. This automated periodic billing and settlement ensures that the sales information system and Profitability Analysis are continually supplied with data from Service Management.
The billing and settlement is executed by the jobs SM_01 and SM_02, which are automatically started by the system at the beginning of each month with the user name IDADMIN (see System → Services → Jobs → Job Overview).
April 2001 17
Customer Service (CS) SAP AG
Note for IDES Processes in the Customer Service Area
Note for IDES Processes in the Customer Service Area
Each IDES process in the area of Customer Service can be executed using data existing in the system, independently from other processes. The sequence of the processes, however, also enables you in some processes to use data that you created in a preceding process. If this is the case, the accompanying process documentation describes both possibilities.
In the process for the controlling of services, the report displays current data even if the preceding processes have not yet been executed. This is because the service contracts in IDES are billed and settled automatically each month.
18 April 2001
SAP AG Customer Service (CS)
Service Processing
Service Processing
Selling a Serialized Product and Creating an Equipment Master Record
Customer Service - Spare Part Delivery
Performing a Service Order and Billing
Creating a Service Order from a Sales Order
Processing Telephone Calls in a Call Center
April 2001 19
Customer Service (CS) SAP AG
Selling a Serialized Product and Creating an Equipment Master Record
Selling a Serialized Product and Creating an Equipment Master Record
Purpose
The customer orders a personal computer. During outbound delivery, serial numbers are used to determine which individual units of the material are to be delivered to the customer. IDES uses equipment as the technical reference object for service processing. This means that you need to create additional equipment data following the outbound delivery to a customer.
Process Flow
You can find the data for this process under .
1. Creating a Sales Order for a Serialized Product
3. Creating a Billing Document
4. Checking the Sales Document Flow (Optional)
5. Creating the Equipment Data
20 April 2001
SAP AG Customer Service (CS)
Data Used During This Process
Data Used During This Process
Field
Data
Description
Order type
TA
Order type (SD)
Sales organization
1000
Sales organization (SD)
Distribution channel
10
Distribution channel (SD)
Division
00
High-tech division (SD)
Sold-to party
1171
Customer number
Material
R-1001
Desktop Computer
Plant
1200
Warehouse number
012
Warehouse Dresden / Atlanta
Business area
8000
Business area
Maintenance planning plant
1200
Planning Plant (PM)
Maintenance plant
1200
Maintenance Plant (PM)
April 2001 21
Customer Service (CS) SAP AG
Creating a Sales Order for a Serialized Product
Creating a Sales Order for a Serialized Product
1. Call up the transaction as follows:
Menu Path
Logistics → Sales and Distribution → Sales → Order → Create
Transaction Code
VA01
2. Enter the following data:
Field
Data
Order type
TA
Sales organization
1000
Distribution channel
10
Division
00
3. Choose .
4. Enter the following data:
Field
Data
Sold-to party
1171
Purch. order no.
TA-1171-SM
Req. deliv. date
Current date + 7 working days
Material
R-1001
Order quantity
2
5. Choose .
6. In the dialog, box choose .
The system produces a BOM explosion. This generates additional items which serve as an explanation.
7. Choose the Shipping tab page, and note the material staging date of the first item.
8. Choose .
9. Make a note of the sales order number.
10. Choose until the overview tree appears.
11. In the dialog box, choose No.
22 April 2001
SAP AG Customer Service (CS)
Creating a Delivery
Creating a Delivery
1. Call up the transaction as follows:
Menu Path
Logistics → Sales and Distribution → Shipping and Transportation → Outbound Delivery → Create → Single Document → With Reference to Sales Order
Transaction Code
VL01N, LT03
2. Enter the following data:
Field
Data
Shipping point
1200
Selection date
Material staging date
Order
Sales order number
From item
No entry
To item
No entry
3. Choose .
You now see the overview screen for the delivery document.
4. Select the first item, then choose Extras → Serial numbers.
The Maintain Serial Numbers dialog box appears.
5. Choose .
6. In the Serial number selection screen area, enter the following data:
Field
Data
Plant
1200
Storage location
0001
7. Choose .
The system produces a list of serial numbers occurring in the specified plant and storage location.
8. Select the first two entries in the list, then choose .
9. Make a note of the selected serial numbers.
10. Choose .
11. Choose Subsequent functions → Create transfer order.
12. In the dialog box, choose Yes.
13. Enter the following data:
Field
Data April 2001 23
Customer Service (CS) SAP AG
Creating a Delivery
Warehouse number
012
Plant
1200
Delivery
Proposed by the system
Foreground/Background
Background
Adopt picking quantity
2
14. Choose .
15. Note the delivery number.
The system creates a transfer order for picking the delivery quantities. The option 2 (Adopt picking quantity) means that the goods issue is posted immediately for that delivery.
16. Choose until the overview tree appears.
24 April 2001
SAP AG Customer Service (CS)
Creating a Billing Document
Creating a Billing Document
1. Call up the transaction as follows:
Menu Path
Logistics → Sales and Distribution → Billing → Billing Document → Create
Transaction Code
VF01
2. Enter the following data:
Field
Data
Document
Your delivery number
3. To display the overview of the billing item, choose .
4. To create the billing document, choose .
You see the number of the new billing document. The system posts the corresponding accounting documents in the background.
5. Choose until the overview tree appears.
April 2001 25
Customer Service (CS) SAP AG
Checking the Sales Document Flow (Optional)
Checking the Sales Document Flow (Optional)
1. Call up the transaction as follows:
Menu Path
Logistics → Sales and Distribution → Sales → Order → Display
Transaction Code
VA03
2. Enter the following data:
Field
Data
Order
Your sales order number
3. Choose .
You now see the document flow for all documents involved in this sales process. To display any of the documents, position your cursor on the relevant line, then choose Display document.
4. Choose until the overview tree appears.
26 April 2001
SAP AG Customer Service (CS)
Creating the Equipment Data
Creating the Equipment Data
Use
When the PC has been delivered to the customer, you create equipment data for the individual items.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Technical Objects → Serial Numbers → List Editing → Change
Transaction Code
IQ08, IQ02
2. Enter the following data:
Field
Data
Material
R-1001
Current customer (in the Serial number selection screen area)
1171
3. To start the serial number selection, choose .
4. Select the serial numbers you have noted.
5. Choose .
6. Choose Equipment view.
You can also maintain the equipment data.
7. Choose the Sales and Distribution tab page.
8. Enter the following data:
Field
Data
Sales org.
1000
Distrib. channel
14
Division
00
9. Choose the Organization tab page.
10. To confirm possible warning messages, choose .
11. Enter the following data:
Field
Data
Company code
1000
Business area
8000
Planning Plant
1200
Planning group
200
April 2001 27
Customer Service (CS) SAP AG
Creating the Equipment Data
Main WorkCtr
PC-SERV / 1200
Catalog profile
PC
12. Choose .
13. To confirm possible warning messages, choose .
14. Choose .
You can now process the second serial number. Make the same entries for this serial number.
15. Choose until the overview tree appears.
28 April 2001
SAP AG Customer Service (CS)
Related IDES Processes
Related IDES Processes
You could now continue with one of the following business processes:
1. Customer Service - Spare Part Delivery
2. Processing a Service Order and Billing
3. Returns and Repair Processing
April 2001 29
Customer Service (CS) SAP AG
Service Management - Spare Part Delivery
Service Management - Spare Part Delivery
Purpose
The customer reports a damaged part on a piece of equipment. The information about the equipment, customer, and damage is stored in a service notification. The object information screen displays the structure of the equipment (material number of the spare parts).
A sales order is generated directly from the notification and processed when the spare part information is entered. When the notification is saved, the sales order is also saved in the background.
Process Flow
You can find the data for this process under .
1. Creating a Service Notification and a Spare Parts Order
2. Creating a Spare Parts Order
3. Creating a Billing Document
Instead of working with the defaulted equipment number, you can also create your own equipment number if you first run the process Selling a Serialized Product and Creating an Equipment Master Record .
30 April 2001
SAP AG Customer Service (CS)
Data Used During This Process
Data Used During This Process
Field
Data
Description
Warehouse number
012
Warehouse Dresden or Atlanta
Plant
1200
Plant of the model company
Material number
R-1001 R-1120
Desktop Computer cable / spare part
Sales organization
1000
Sales organization (SD)
Distribution channel
14
Distribution channel (SD)
Division
00
Division (SD)
Sold-to party
1171
Customer number
Equipment
10003562 or equipment from previous process
Equipment (PM)
Planning plant
1200
Planning plant (PM)
April 2001 31
Customer Service (CS) SAP AG
Creating a Service Notification and a Spare Parts Order
Creating a Service Notification and a Spare Parts Order
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Notification → Create (Special) → Problem Notification
Transaction Code
IW54
2. Enter the following data:
Field
Data
Equipment
10003562 or equipment from previous process 3. Choose .
4. Choose the Contact person address tab page.
5. Enter the following data:
Field
Data
Description (notification)
Defective cable, replacement required.
Contact person
Choose a contact person using the F4 help
You access the list of contact persons by positioning your cursor in the second entry field of the Contact person line and choosing the F4 help button.
In the Hit List dialog box, position your cursor on a contact person and choose .
6. Choose .
7. To check the object information for your equipment, in the Reference object section, choose .
8. In the Object Information dialog box, choose (Obj. Display section).
The system displays information about spare parts that you can use for your object.
9. To return the to the Create Service Notification: Service Notification screen, choose , then choose.
10. To create the spare parts order for the customer equipment directly from the service notification, choose Service notification → Create sales order → Standard.
11. Enterr the following data:
Field
Data
Purch. order no.
ERS-1171-SM
Material
R-1120
Order quantity
1
32 April 2001
SAP AG Customer Service (CS)
Creating a Service Notification and a Spare Parts Order
12. Choose .
13. Choose the Shipping tab page and note the material availability date.
14. Choose .
15. Choose .
The system saves the notification and the sales order. Make a note of the notification and sales order numbers.
16. Choose until the overview tree appears. In the dialog box, choose No.
April 2001 33
Customer Service (CS) SAP AG
Creating a Spare Parts Order
Creating a Spare Parts Order
1. Call up the transaction as follows:
Menu Path
Logistics → Sales and Distribution → Shipping and Transportation → Outbound Delivery → Create → Single Document → With Reference to Sales Order
Transaction Code
VL01N, LT03
2. Enter the following data:
Field
Data
Shipping point
1200
Selection date
Material availability date
Order
Number of your order
From item
No entry required
To item
No entry required
3. Choose .
4. Choose Subsequent functions → Create transfer order.
5. In the dialog box, choose Yes.
6. Enter the following data:
Field
Data
Warehouse number
012
Plant
1200
Delivery
Proposed by the system
Foreground/background
Background
Adopt pick. quantity
2
7. Choose .
The system creates a transfer order for picking the delivery quantity. The option 2 (Adopt picking quantity) means that the goods issue is posted immediately for that delivery.
8. Note down your delivery number.
9. Choose until the overview tree appears.
34 April 2001
SAP AG Customer Service (CS)
Creating the Billing Document
Creating the Billing Document
1. Call up the transaction as follows:
Menu Path
Logistics → Sales and Distribution → Billing → Billing Document → Create
Transaction Code
VF01
2. Enter the following data:
Field
Data
Document
Your delivery number
3. To display the overview of the billing items, choose .
4. Choose .
The system posts the corresponding accounting documents in the background.
5. Choose until the overview tree appears.
April 2001 35
Customer Service (CS) SAP AG
Performing a Service Order and Billing
Performing a Service Order and Billing
Purpose
In response to a problem notification, a service order is created for the repair of an installed equipment at the customer site. After completion of the service order, the repair is billed to the customer.
You can find more information about this process under .
Process Flow
You can find the data for this process under .
1. Creating the Initial Situation
2. Entering a Problem Notification and Creating a Service Order
5. Creating a Billing Request (Resource-Related Billing)
6. Creating a Billing Document
7. Settling and Completing the Service Order
8. Displaying Line Items in Profitability Analysis
9. Displaying a CS Report in Profitability Analysis
Instead of working with the default equipment number, you can also create your own equipment number if you first run the Selling a Serialized Product and Creating an Equipment Master Record process.
36 April 2001
SAP AG Customer Service (CS)
April 2001 37
Customer Service (CS) SAP AG
Additional Process Information
Additional Process Information
The following, additional information is aimed at IDES users who are already with familiar with Customizing for the application components CS (Customer Service) and SD (Sales and Distribution). The aim is to show the billing of a service order from a Customizing perspective using the data contained in this process. Because this text refers to this IDES demo, you should read it after completing the process flow.
Dynamic Item Processor Profile (DIP Profile)
Derivation of Sales Materials
When you execute the service order, costs are incurred due to internal activities, external activities, or material consumption. These costs are posted to the service order, where they form the basis for a billing request. The service order is billed to the customer using the billing document generated by the billing request. The cost data of the order are converted to billing request items through dynamic items. These dynamic items are created when the billing request is generated. You copy information from the service order. The R/3 System uses this information to generate the billing request items. The rules for structuring the dynamic items and for converting these items into material numbers for the billing request items are defined) in Customizing using the dynamic item processor profile (DIP profile).
You also use Customizing to determine that DIP profile 00000001 is the automatic default for service order type SM02, which was used to create the service order in this IDES process.
(see SAP Reference IMG: Plant Maintenance and Customer Service → Maintenance and Service Processing → Maintenance and Service Orders → Functions and Settings for Order Types → Credit Limit Checks, Sales Document Types for Service Orders).
In this IDES process, order costs are incurred due to two activity confirmations with activity type 1410 for cost center 4100, and due to the consumption of materials R-1150 and R-1160. The rules of the DIP profile 00000001 are explained based on this information.
(see SAP Reference IMG: Plant Maintenance and Customer Service → Maintenance and Service Processing → Basic Settings → Quotation Creation and Billing for Service Orders → Profiles for Quotation Creation, Billing, Results Analysis).
When creating the billing request, the system takes the entries for usage 1 (that is, billing and calculation of profits).
On the level Sources, it has been defined for this use that source 0001 (that is, actual costs line items) is evaluated for the creation of dynamic items.
The line items created due to the first activity confirmation contains the information that the costs were incurred under activity type 1410 in cost center 4100. On the level Characteristics, the characteristics cost center and activity type has been marked as relevant for usage 1. Thus, the system copies activity type 1410 and cost center 4100 from the line item to the dynamic item. They can now be used for further processing. Both characteristics are used to derive a material for the billing request (see indicator Material determination). With regard to the characteristics relevant for the creation of a dynamic item, the line item of the second activity confirmation is identical to the first line item. The system therefore creates one common dynamic item for both line items that displays the sum of the costs incurred.
On the level Material determination, the system lists the material SM-REPHOUR. It is therefore one of the materials intended for transfer to a billing request item.
38 April 2001
SAP AG Customer Service (CS)
Additional Process Information
On the Criterion level, it has been defined that this material is derived from the criteria cost center and activity type. The criterion cost center is met if the cost center of the dynamic item corresponds to a value of set SM-CC1. The set SM-CC1 contains the cost center 4100.
(see: Accounting → Financial Accounting → Special Purpose Ledger → Tools → Set maintenance → Sets → Display).
The criterion Activity type is met if the activity type of the dynamic item corresponds to a value of set SM-AT1. Set SM-AT1 contains the value 1410. Both criteria have been met in this example. The material number SM-REPHOUR is therefore allocated to the dynamic item.
The line item created due to the withdrawal of material R-1150 contains, for example, information about the cost element and the material number. The characteristic Cost element and Material are relevant for the creation of dynamic items and are therefore copied to the dynamic item. The characteristic Cost element is used for material determination. On the level Material determination you will find an entry without a material number where the indicator Direct material is set. This indicator ensures that the R/3 System assigns the material contained in the line item to the dynamic item. On the level Criteria, it is defined that this type of assignment only occurs if the line item was posted to the cost element in the set CO-PC-MAT. This set comprises the cost elements used to post material consumption. In this example, the withdrawal of material R-1150 was posted under cost element 410000. This cost element belongs to the cost element set CO-PC-MAT. This means that the criteria for the material determination have been fulfilled, and that the material R-1150 contained in the line item is transferred to the dynamic item.
The line items for the consumption posting of material R-1160 leads to a separate dynamic item as the characteristic Material has a different value. The material determination is processed according to the same logic described above.
Billing Form
The billing form for the service order decides whether the order is billed as flat rate or resource-related. To make this distinction, information about the billing form must be available when the billing request is created. For this reason the billing form is selected as a relevant characteristic.
Product
The characteristic Product is marked as relevant for further processing. This control data is a prerequisite for copying a service product specified in the service order to the billing request.
Accounting Indicator
When posting the material consumption for material R-1150, the system enters the accounting indicator K1 (goodwill 100%). This entry is copied to the line item. The accounting indicator is also a relevant characteristic in the DIP profile 00000001 for usage 1. The entries concerning the accounting indicator are therefore copied from the line item to the dynamic item. The accounting indicator can thus be used to price the billing request item resulting from the dynamic item. The costing sheet PSER02 used in the billing request contains the condition type KBM1 (goodwill/warranty). The access sequence assigned to this condition type allows you to enter condition records dependent on the accounting indicator. In this example, there is a condition record that determines a 100 per cent deduction if the accounting indicator K1 is available.
To avoid the summarization of several dynamic items with various accounting indicators in one billing request item, the indicator No summarization was set in the DIP profile for the characteristic Accounting indicator.
April 2001 39
Customer Service (CS) SAP AG
Additional Process Information
Transferring Costs into the Billing Request
You can also determine for which condition types entries can made for the document type of the billing request on the overview screen of the dynamic items. You must specify the defined condition type if the costs of the dynamic items should be copied to the price determination of the respective billing request items. In this example, the costs are copied to the condition type EK01 (see SAP Reference IMG: Plant Maintenance and Customer Service → Maintenance and Service Processing → Basic Settings → Quotation Creation and Billing for Service Orders → Assign Conditions to Sales Document Types).
Item Category Determination
When a service order is billed, the billing form determines whether the order is billed at flat rate (billing form = 01) or resource-related (billing form = 02). In this IDES process, we offer an example for resource-related billing. We explain item category determination for creating the billing request for this example:
The billing form is not explicitly specified. In this case, the system assumes a resource-related billing. The service order is created without entering a service product in this example. When creating the billing request, the dynamic items become the main items of the sales document. With resource-related billing, the item category determination for the dynamic items is processed with the item usage SEIN.
Item category determination for items with material SM-REPHOUR is executed using the following entry:
Sales document type LV + item category group LEIS + usage SEIN → L2N.
Item category determination for items with material R-1150 or R-1160 is executed using the following entry:
Sales document type LV + item category group NORM + usage SEIN → L2N.
Item category L2N is priced, then it is billed.
(See SAP Reference IMG: Sales and Distribution → Sales → Sales Documents → Sales Document Item → Assign Item Categories or Define Item Categories).
40 April 2001
SAP AG Customer Service (CS)
Data Used During This Process
Data Used During This Process
Field
Europe
Description
Plant
1200
Material numbers
R-1150
R-1160
SM-REPHOUR
SM-PCREP
Disk drive / spare part hard disk drive / spare part repair hours
Service product
Service order type
SM02
Service order type (revenues)
Sales organization
1000
Sales organization (SD)
Distribution channel
14
Distribution channel (SD)
Division
00
Division (SD)
Sold-to party
1171
Customer number
Equipment
10003562 or equipment from previous process
Planning Plant
1200
Maintenance plant
1200
Business area
8000
Operating concern
IDEA
Global IDES
Type of profitability analysis
Costing-based
Report
IDES-090
SM reporting
April 2001 41
Customer Service (CS) SAP AG
Creating the Initial Situation
Creating the Initial Situation
Use
You start a CATT procedure that performs an inventory posting for the materials used in the process. This ensures that the process can run through several times.
Procedure
6. Call up the transaction as follows:
Menu Path
Tools → ABAP Workbench → Test → Test Workbench → CATT Extended
Transaction Code
SCAT
7. Enter the following data:
Field
Data
Test case
ZIDES_SMASC03 8. Choose .
9. Enter the following data:
Block
Option
Log type
W/o
Processing mode
Background
Variants
W/o
10. Choose .
In the bottom part of the screen, the system displays which transactions are being processed. When the process flow is completed, the system notifies you that a document number has been assigned for the inventory posting.
11. Choose until the overview tree appears.
42 April 2001
SAP AG Customer Service (CS)
Entering a Problem Notification and Creating a Service Order
Entering a Problem Notification and Creating a Service Order
Use
The customer informs you about a defective piece of equipment. You accept a problem notification and enter the notification data in the system. The service order is created directly from problem notification processing.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Notification → Create (Special) → Problem Notification
Transaction Code
IW54
2. Enter the following data:
Field
Data
Equipment
10003562 or equipment from previous process 3. Choose .
The system copies further information from the equipment master record into the notification (for example, sold-to party, functional location).
4. Enter the following data:
Field
Data
Notification (in the first line)
Hard disk + CD disk drive defective
5. Choose .
6. Check the object information, by selecting in the section Reference object.
The dialog box informs you which notifications and orders were entered regarding this equipment.
7. Choose .
8. To create a service order directly from notification processing, choose .
The Create order dialog box appears.
9. Choose .
10. In the First operation screen area, enter the following data:
Field
Data
Operation
Check/change hard disk + CD disk drive 11. Choose .
April 2001 43
Customer Service (CS) SAP AG
Entering a Problem Notification and Creating a Service Order
The system proposes further information necessary from the equipment master record into the service order (for example, work center).
12. Choose Extras → Sales data.
You can recognize that the service order is assigned to a sales organization (that is, a combination of the sales organization, distribution channel, and division). This proposal was also taken from the equipment master record data. The assignment of a sales area is required for service order billing.
13. Choose .
14. To put the order in process, choose .
15. Select W/o print, then choose .
16. To confirm possible warning messages, choose .
The system saves the service order and the corresponding notification.
17. Note the number of the order.
18. Choose , untli the overview tree appears..
19. In the dialog box, choose No.
44 April 2001
SAP AG Customer Service (CS)
Processing a Service Order
Processing a Service Order
Use
In the following process, you play the role of a service employee who is responsible for repairing the equipment. First of all, you plan the work to be performed in the service order.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Order → Service Order → Change
Transaction Code
IW32
2. Enter the following data:
Field
Data
Order
Number of your service order
3. Choose .
4. To check the object information for your piece of equipment, choose in the Reference object section.
The notification that triggered the service order is listed here.
5. Choose .
6. Enter the following data:
Field
Data
Work durtn (in the section First operation)
2
7. Choose .
8. Choose the Components tab page.
9. To call up the Structure list, choose List.
The structure list informs you about the components of the equipment to be repaired. The materials necessary for processing the repairs can be copied from this list into the service order.
10. Select the materials R-1150 and R-1160, then choose .
11. Enter the following data:
Field
Data
SLoc (in the line for material R-1150)
1500 (overwrite the default value)
SLoc (in the line for material R-1160)
1500 (overwrite the default value)
12. Choose . April 2001 45
Customer Service (CS) SAP AG
Processing a Service Order
The system calculates the planned costs of the order according to the entries made for the planned working hours and the materials necessary.
13. Choose Extras → Cost reports → Plan/actual comparison.
The planned costs are displayed under the corresponding cost element types.
14. Choose .
15. Choose .
16. Choose until the overview tree appears.
46 April 2001
SAP AG Customer Service (CS)
Confirming a Service Order
Confirming a Service Order
Use
You confirm the effort necessary for the repair now. It is assumed that you enter the effort in two partial confirmations. All materials used for the repair are also confirmed. You decide whether the floppy disk drive is exchanged for goodwill.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Confirmation → Entry → Individual Confirmation (Time)
Transaction Code
IW41
2. Enter the following data:
Field
Data
Order
Your order number
3. Choose .
4. Enter the following data:
Field
Data
Actual work
1
Final confirmat
Deselect
Clear open res.
Deselect
Work start
Current date
Work end
Current date
5. Choose .
6. Choose .
7. Enter the following data:
Field
Data
Order
Your order number
8. Choose Parameters.
9. In the Goods movements area, select All comps, then choose .
Setting this indicator causes the system to display all the materials assigned to the operation to be confirmed in the goods movement overview.
10. Choose .
April 2001 47
Customer Service (CS) SAP AG
Confirming a Service Order
11. Enter the following data:
Field
Data
Actual work
2
Work start
Current date
Work end
Current date 12. Choose .
13. Choose Goods movements.
The materials assigned to the operation are listed. The withdrawal of the materials listed here is posted when the confirmation is saved.
14. Move the screen section to the right by scrolling the horizontal scrollbar until you can see the column Accounting Indicator (AInd).
15. Enter the following data:
Field
Data
AInd (in the line of material R-1150)
K1
Using the accounting indicator, you can differentiate between costs in service processing. When billing the service order, the accounting indicator K1 leads to a price reduction of 100 %. All costs marked with this accounting indicator are therefore not billed to the customer.
16. Choose .
17. Choose until the overview tree appears.
18. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Order → Service Order → Change
Transaction Code
IW32
19. Enter the following data:
Field
Data
Order
Your order number
20. Choose .
21. Choose Extras → Cost Reports → Planned/actual comparison.
The completion confirmation has caused he order to be debited with actual costs. These are compared to the planned costs.
22. Choose .
23. To complete your order, choose .
24. In the dialog box, choose .
48 April 2001
SAP AG Customer Service (CS)
Confirming a Service Order
25. Choose until the overview tree appears.
April 2001 49
Customer Service (CS) SAP AG
Creating a Billing Request (Resource-Related Billing)
Creating a Billing Request (Resource-Related Billing)
Prerequisites
In this step, you create a billing request for the processed service order. No particular billing form is specified in the service order. In this case, the system assumes a resource-related billing.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Completion → Create Billing Request → Process Individually
Transaction Code
DP90, VA02
2. Enter the following data:
Field
Data
Service order
Number of your service order
Posting date to
Todays date
3. Choose Expenses.
The service order costs incurred due to material consumption and the repair hours are listed. The costs incurred due to the work hours are summarized under the material number SM-REPHOUR. The costs incurred due to the material consumption are displayed under each respective material number.
4. Move the screen section to the right by scrolling the horizontal scrollbar until you can see the column AInd (Accounting Indicator).
The system transfers the information that the accounting indicator K1 (goodwill 100%) has been specified on confirmation of the withdrawal of the hardiest.
5. Choose Sales price.
The Billing request for resource-related billing document : Sales price screen appears.
6. Position your cursor on the billing request row, then choose .
The system displays the billing request items that are generated when you save on the second level. The expenses and value (column Net value) with which the expenses are billed are compared with one another.
7. To call up the sales price determination, double-click on the row for material R-1150 (floppy disk drive).
The costs have been copied to the condition EK01 (actual costs). The material has a price (condition type PR00) with which it is invoiced. Due to accounting indicator K1, however, the invoice is issued with a price reduction of 100% with condition type KBM1 (goodwill/guarantee).
8. Double-click on the row for material R-1160 (harddisk).
50 April 2001
SAP AG Customer Service (CS)
Creating a Billing Request (Resource-Related Billing)
The service order costs have been copied to the condition EK01 (actual costs). A price exists for the material (condition type PR00). The material is billed with this price.
9. Double-click on the row for material SM-REPHOUR (Repair Hour).
The service order costs have been copied to the condition EK01 (actual costs). The material has a sales price (condition type PR00) with which it is invoiced.
10. Choose Billing request.
The Create billing request dialog box appears.
11. Choose Yes.
The billing request created by the system is automatically displayed due to a default setting.
12. Note the number of the billing request in the Deb.Memo Req.f. Ctrct field.
13. The billing request is initially blocked for billing. To delete this billing block, enter the following data:
Field
Data
Billing block
Delete existing block 14. Choose .
15. Choose until the overview tree appears.
April 2001 51
Customer Service (CS) SAP AG
Creating a Billing Document
Creating a Billing Document
Use
You create the billing document for the checked billing request.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Completion → Billing Document → Create
Transaction Code
VF01
2. Enter the following data:
Field
Data
Document
Number of the billing request 3. Choose .
The system displays an overview of the billing items.
4. Choose .
5. Choose until the overview tree appears.
52 April 2001
SAP AG Customer Service (CS)
Settling and Completing the Service Order
Settling and Completing the Service Order
Use
All costs and revenues posted to the order are transferred to the profitability analysis via a settlement. As no further costs or revenues occur for the service order, you complete it from a business perspective.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Order → Service Order → Display
Transaction Code
IW33
2. Enter the following data:
Field
Data
Order
Number of your service order
3. Choose .
4. Choose Extras → Cost reports → Planned/actual comparison.
The revenues earned are posted to the order when the billing document is created.
5. Choose until the overview tree appears.
6. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Completion → Order Settlement → Settle Individually
Transaction Code
KO88
7. If the Set controlling area dialog box appears, enter the following data and choose :
Field
Data
Controlling area
1000
8. Enter the following data:
Field
Data
Order
Number of your service order
Settlement period
Current period
Fiscal year
Current fiscal year
Test run
Deselect
9. Choose .
April 2001 53
Customer Service (CS) SAP AG
Settling and Completing the Service Order
If you have previously processed a service order that belonged to another controlling area than your current service order, the system will at first display an error message. Should this occur, choose Extras → Controlling Area, then enter 1000. To continue with the order settlement, choose .
10. To call up the detail list, choose .
11. Position your cursor on the service order number row and choose Sender.
The system lists all values that are posted from the service order to the profitability segment.
12. Choose until the overview tree appears.
13. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Order → Service Order → Change
Transaction Code
IW32
14. Enter the following data:
Field
Data
Order
Number of your service order
15. Choose .
16. Choose Extras → Cost reports → Planned/actual comparison.
Due to the order settlement, the service order was credited.
17. Choose .
18. Choose Order → Functions → Complete → Complete (business).
The system saves your order.
19. Choose until the overview tree appears.
The operative service process is complete after settlement. Both steps deal with the transaction from the Profitability Analysis view CO-PA). Firstly, you deal with the line item generated during settlement. You then execute a report that analyzes all present profitability data relating to services. The values for the present process flow into this report.
54 April 2001
SAP AG Customer Service (CS)
Displaying Line Items in Profitability Analysis
Displaying Line Items in Profitability Analysis
Use
The costs and revenues are stored under record type C (order and project settlement) in Profitability Analysis through the settlement of the service order.
Procedure
20. Call up the transaction as follows:
Menu Path
Accounting → Controlling → Profitability Analysis → Information System → Display Line Items → Actual
Transaction Code
KE24
If you are processing an operating concern in this session for the first time, the system displays the dialog box Set Operating Concern.
21. Enter the following data:
Field
Data
Operating concern
IDEA
Type of profitability analysis
Costing-based
22. Choose .
This dialog box is only displayed once per session. Once you have made your selection, the system assumes that you will only work in this operating concern and type in this session.
23. Enter the following data:
Field
Data
Currency type
B0
Date created
Todays date
Entered by
Your user name
24. Choose .
25. In the dialog box, choose .
You find the item or items (depending on whether you created the billing request according to variant A or B or both versions) that has/have the record type C and that was/were posted to CO-PA via settlement from Customer Service.
26. Double-click on one of these line items.
You are now on the initial selection screen for the line items. Here you can see all the characteristics that can be analyzed in Profitability Analysis. The values for these characteristics were derived from the customer and material master records, the SD
April 2001 55
Customer Service (CS) SAP AG
Displaying Line Items in Profitability Analysis
partner functions (such as the sales representative), or from CO-PA-specific characteristics.
For example, you see the customer, industry, product, and so on.
To view further characteristics, choose .
27. Choose the Value fields tab page.
You can see detailed information about the billed quantities, revenues, discounts, and detailed product cost components that were derived from SD and CO-PC. Note that the list of value fields spans several screens.
28. To scroll through the value field screens, choose .
You see the revenue generated due to order billing.
The costs incurred due to goodwill relate to the usage of materials exchanged out of goodwill.
The customer discount is calculated from the discount of 100% which has been granted out of goodwill. Material usage is made up of the costs that were generated through the use of materials for the service order. Excluded from this is any material exchanged for reasons of goodwill.
Sales commission is calculated by valuating anticipated costs from Profitability Analysis.
Maintenance costs represent the costs of services provided by a service technician.
29. Choose until the overview tree appears.
56 April 2001
SAP AG Customer Service (CS)
Displaying a CS Report in Profitability Analysis
Displaying a CS Report in Profitability Analysis
Use
The report IDES-090 Reporting Service Management uses different accounts receivable and service products to demonstrate how the reporting procedure for service management can be structured. The revenues and costs produced in the previous steps have been made compatible with reporting and also analyzed in the form of key figures.
Procedure
1. Call up the transaction as follows:
Menu Path
Accounting → Controlling → Profitability Analysis → Information System → Execute Report
Transaction Code
KE30
2. Selec the IDES-090 report and choose .
3. Enter the following data:
Field
Data
Fiscal year
Current fiscal year
From period
1
To period
Current period 4. Choose .
The report data is selected again.
You arrive at the basic screen of the report. In the report header, you see the dimensions defined for this report: sales organization 1000 Germany Frankfurt, and distribution channel 14 Service.
Beneath the report header, you find the navigation field which enables you to navigate through the individual service products. In the form of key figures, you find revenues, sales deductions, costs and the resultant contribution margins which are displayed in the additional columns and are cumulated for the individual accounts receivable.
In the first column, you find the customer "Hitech" (customer number 1171) for which you have created the service order or order(s).
For more information about navigating within a report, see Executing an Existing Report in Profitability Analysis and Getting to know Reporting Functions .
5. Choose Report → Exit.
6. In the dialog box, choose Yes.
7. Choose until the overview tree appears.
April 2001 57
Customer Service (CS) SAP AG
Displaying a CS Report in Profitability Analysis
58 April 2001
SAP AG Customer Service (CS)
Returns and Repair Processing
Returns and Repair Processing
Purpose
The service department of the IDES AG receives a repair request from a customer. The customer sends the defect piece of equipment to our company. This equipment is then checked technically and subsequently we process the repair. After completion of the repair, the piece of equipment is delivered to the customer. The repair will then be invoiced.
You can find more information about this process under .
Process Flow
You can find the data for this process under .
2. Creating the Service Notification and the Repair Request
3. Posting the Goods Receipt of a Piece of Equipment to be Repaired
4. Processing the Technical Check
5. Displaying the Repair Request and the Service Order
7. Processing and confirming the Service Order
8. Technically Completing the Service Order
9. Delivering the Repaired Piece of Equipment
10. Creating the Billing Request
11. Invoicing the Repair Request
12. Settling and Completing the Service Order
13. Analyzing the Result of the Repair request
April 2001 59
Customer Service (CS) SAP AG
Additional Process Information
Additional Process Information
The following information is directed towards IDES users with a customizing background knowledge of the application components SD and CS. Its objectives are to explain the determination of the item categories in the repair request as well as the control of the repair scheme. The text uses the concrete IDES demo. Therefore it is advised to read it after completing the process chain.
Sales Document RAS (Repair Service)
The repairs processing of the present IDES process is based on the sales document RAS. In this type of sales document, the material number of the service product is leading. The service product is coupled to data that is used for the automatic creation of the service order when starting the repair.
The data transferred to the service order via the service product can be seen in the system as follows:
Logistics → Customer Service → Service Processing → Environment → Sales and distribution → Billing Document → Service Products.
Repair Maintenance Request Item (IRRS)
When creating the repair request using the sales document RAS, the system creates a repair maintenance request item with the item category IRRS. This repair maintenance request item administers the expenses and revenues of the repair as well as the sales order stock of the pieces of equipment to be repaired. The item category is determined via the item category group of the service products SM-PCREP due to the following system settings:
Sales document RAS + item category group LEIS → IRRS.
The item category IRRS controls that the repair is invoiced according to the expenses caused by the repair. (form of billing = 02). The repair maintenance request item itself is not relevant for billing (billing relevance = blank). The rules for the billing according to expenses are determined via the Dynamic item processor profile that is assigned to the item category (DPP profile = 00000002). In the item category, we also embodied the repair scheme 0001 that controls which repair operations can be processed at a specific time within repairs processing:
(see SAP Reference IMG → Sales and distribution → Sales → Sales Document → Sales document Item → Assign item category or Define item category).
Returns Item (IRRE)
When creating the repair maintenance request item the repairs receipt should take place at the same time. Repair scheme 0001 is defined so that the operation Returns (101) is possible as well at the same time. Due to the default characteristic set for this operation within the scheme, the system automatically generates the returns item. One can set default characteristics for operations that are not linked to completion confirmations of inspection lots or service orders:
(see SAP Reference IMG → Sales and distribution → Sales → Sales Documents → Repairs Processing → Define repair procedures).
The item category determination takes place in connection with the item category group of the equipment material R-1001: sales document RAS + item category group NORM + usage R101 + item category of the main item IRRS → IRRE.
60 April 2001
SAP AG Customer Service (CS)
Additional Process Information
The usage is composed of the operation number and starts with an R.
Repair Item (IRRP)
Within the framework of the technical check, the system processes a write-off of the equipment materials of the stock in quality inspection. The equipment can either be posted to the blocked stock or the unrestricted-use stock or can be scrapped. The system derives a key from each respective goods movement (01 = repair; 02 = not to be repaired/delivered; 03 = scrapped). In combination with the time start of repair that has been reached by the end of the completion of the technical check, the system determines the next operation via this key in the repair scheme of the repairs processing and proposes it in the repair request. In the displayed IDES process, the system makes a posting to the blocked (i.e. to be repaired) stock. From here, the system derives the key 01. The time start of repair earmarked the operation 102 (repair) for this key. As we did not set the characteristic manual (manual processing not necessary) for this operation, the system automatically creates another sub-item in the repair request. The item category IRRP is determined via the following entry in the item category assignment: Sales document RAS + item category group LEIS + usage R102 + item category of main item IRRS → IRRP.
The system derives the schedule line category CD (without delivery) from the item category IRRP:
(see SAP Reference IMG → Sales and distribution → Sales → Sales Document → Schedule Lines → Define Schedule Line Categories or → Assign Schedule Line Categories).
The requirement type SERP (maintenance service) is not as usually derived from the strategy group of the material but directly from the operation:
Item category IRRP + availability indicator Blank → requirements type SERP / source 1:
(see SAP Reference IMG → Sales and distribution → Basic Functions → Availability Check and Transfer of Requirements → Transfer of Requirements → Determination of Requirement Types Using Transaction).
The requirements class 204 is assigned to requirements type SERP. This requirements class controls, due to assembly type 2 and the assigned order type, SM03 (service order/repairs processing) that the system generates a service order of this order type by taking the repair item of the sales and distribution document:
(see SAP Reference IMG → Sales and distribution → Basic Functions → Availability Check and Transfer of Requirements → Transfer of Requirements → Define requirements classes or Define Requirements Classes).
Delivery Item (IRAL)
We coupled the technical completion of the service order to the time Repair confirmation. All equipment in our demo have been posted from the blocked stock into the unrestricted-use stock beforehand. The system derives the key 04 (repaired/to be delivered) from this type of goods movement. For this combination of time and key, the repair scheme intended the operation Delivery (103). As we did not set the characteristic manual (manual processing not necessary) for this operation, the system automatically creates another sub-item in the repair request:
Sales Document RAS + item category group NORM + Usage R103 + item category of the main item IRRS → IRAL.
April 2001 61
Customer Service (CS) SAP AG
Additional Process Information
Billing Item (IRIN)
When creating the billing request on basis of the service order, the cost information of the order is converted into sub-items for the repair maintenance request item.
Items created due to the Dynamic item for the material consumption and the working hours are assigned to the item category determination with usage SEIN:
Sales document RAS + item category group NORM or LEIS + Usage SEIN + item category of the main item IRRS → IRIN.
The items of item category IRIN are billed order-related. The pricing is active but not statistical.
62 April 2001
SAP AG Customer Service (CS)
Data used during this Process
Data used during this Process
Field
Data
Description
Material
R-1001
Personal Computer
Order type
RAS
Repair Service
Sales organization
1000
Sales Germany
Distribution channel
14
Service
Division
00
Cross-division
Sold-to party
1177
Customer
Material
R-1150
spare part
Material
R-1111
spare part
Delivery type
LR
Returns delivery
Shipping point
1200
shipping point in plant 1200
Plant
1200
Plant
Storage location
0001
storage location in plant 1200
Warehouse number
012
warehouse Lean WM
Controlling area
1000
Controlling area Europe
April 2001 63
Customer Service (CS) SAP AG
Activating the QM Check
Activating the QM Check
Use
A pre-requisite for executing this process is the activation of QM inspection type 05 (inspection for other goods receipt) in the material master of used material R-1001. This is done within this step.
So that the run of other IDES processes using material R-1001 is not impaired, it is important to process Deactivating the QM Check even if you finish it early. If you set up a stock in quality inspection already, due to the goods receipt of the equipment to be repaired, it is necessary to execute the process step Processing the Technical Check as well. Here, the stock in quality inspection is reduced. A deactivation of the inspection is only possible if the system contains no stock in quality inspection.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Quality management → Quality planning → Logistics Master Data → Material → Change
Transaction Code
MM02
2. Enter the following data:
Field
Data
Material
R-1001
3. Choose Select view(s).
4. Enter the following data:
Field
Data
Quality Management
Select
5. Choose .
6. In the dialog box, enter the following data:
Field
Data
Plant
1200
7. Choose .
8. Choose Insp.setup.
9. Enter the following data:
Field
Data
Active (in the line inspType 05)
Select
10. Choose .
64 April 2001
SAP AG Customer Service (CS)
Activating the QM Check
11. Choose .
12. Choose until the overview tree appears.
April 2001 65
Customer Service (CS) SAP AG
Creating the Service Notification and the Repair Request
Creating the Service Notification and the Repair Request
Use
The customer notifies the breakdown of three pieces of equipment and the service department dispatches this equipment for repair. You receive the malfunction message and enter a Repair request in the system.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Notification → Create (General)
Transaction Code
IW51, IW53, VA03
2. Enter the following data:
Field
Data
Notification type
S4
This type of notification enables the entry of a material number as reference object.
3. Choose .
4. Note the notification number.
5. Enter the following data:
Field
Data
Sold-to party
1177
Material
R-1001
Description (in the block Subject)
R-1001: Returns and Repair
6. Choose .
7. In the action box, choose Create repair order.
8. Enter the following data:
Field
Data
Order type
RAS
Sales org.
1000
Distr channel
14
Division
00
Sold-to party
1177 (default)
PO number
Notification number (default) 66 April 2001
SAP AG Customer Service (CS)
Creating the Service Notification and the Repair Request
PO date
Current date
Material
R-1001 (default)
Order quantity
3
9. Choose Notification and order.
10. Choose Service notification → Display.
11. Enter the following data:
Field
Data
Notification number
Noted Notification number
12. Choose Notification.
13. To display the Document flow, choose .
14. Position your cursor on the line for the sales order and choose Display document.
The notification number has been transferred to the repair request as the order number. In the item displayed, you can see the detailed data of the repair request of the customer. The defect personal computers are listed as equipment material in this repair maintenance request item.
15. Select the item and then select Repairs.
The system proposes a returns for the piece of equipment to be repaired as the next operation within the repairs processing (see characteristic Returns in the block Overview of repair request). The business decision to process the proposed returns operation has been made by the system automatically (see RepStatus).
16. Choose .
17. Choose Edit → Display criteria → All items.
Due to the decision made to process the returns operation, the system created a sub-item for the repair maintenance request item. It contains the necessary information for the creation of the returns delivery.
18. Note the Repair request number given in the Repairs/ Service field.
19. Choose until the overview tree appears.
April 2001 67
Customer Service (CS) SAP AG
Posting the Goods Receipt of a Piece of Equipment to be Repaired
Posting the Goods Receipt of a Piece of Equipment to be Repaired
Use
The pieces of equipment to be repaired are delivered. In the returns delivery, enter the serial numbers of the devices. They are posted to the non-valuated stock as sales order stock using the number of the Repair requests. At the same time, the system creates an inspection lot on the basis of which the technical check of the devices will take place.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Service Processing node, choose Order → Customer Repair → Returns Delivery
Transaction Code
VRRE, VL01
2. Enter the following data:
Field
Data
Repair request
Noted number of the repair request
Delivery type
LR
Shipping point/ recei
1200
3. Choose .
4. Select the item and choose Item → Serial numbers.
5. Choose .
6. Enter the following data:
Field
Data
Period from
Default
Partner (first field)
Sold-to party (possible entries button)
Partner (second field)
1177
7. Choose .
The system lists all serial numbers of material R-1001 that were delivered to customer.
8. Select three entries for serial numbers.
9. Choose .
10. In the dialog box, choose .
The System lists the selected serial numbers.
11. Choose .
12. Choose Edit → Post goods issue.
68 April 2001
SAP AG Customer Service (CS)
Posting the Goods Receipt of a Piece of Equipment to be Repaired
In the case of returns, the function done before posts a goods receipt.
13. Note the delivery number.
14. Choose until the overview tree appears.
April 2001 69
Customer Service (CS) SAP AG
Processing the Technical Check
Processing the Technical Check
Use
After the goods receipt has been posted, execute a technical check of the devices, based on the goods receipt posting of the inspection lot created. In the framework of this check, you will decide what operations are necessary in the further run of the repairs processing.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Service Processing node, choose Order → Inspection Processing → Usage Decision → Enter
Transaction Code
QA11
2. Choose .
3. Enter the following data:
Field
Data
UD Code (Usage decision Code)
A
4. Choose the Inspection lot stock tab page.
5. Enter the following data:
Field
Data
To blocked / Repair
3
The technical check made clear that all devices send by the customer by the customer, can be repaired. Therefore, you post 3 pieces of equipment from the stock in quality inspection into a blocked repair stock.
6. Choose Serial numbers.
7. To confirm possible warning messages, choose .
You can see that the serial numbers of the devices have been transferred to the inspection lot.
8. Choose .
9. Choose .
10. Choose until the overview tree appears.
70 April 2001
SAP AG Customer Service (CS)
Displaying the Repair Request and the Service Order
Displaying the Repair Request and the Service Order
Use
From the transfer posting of the checked devices the blocked repair stock, the system derives a new operation Repair in the order. The decision to execute this operation has been made automatically due to the settings in the repair scheme, the repairs processing is controlled by. The execution of the repair is done with the help of a service order.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Service Processing node, choose Order → Customer Repair → Display
Transaction Code
VA03
2. Enter the following data:
Field
Data
Order
Noted number of the Repair request
3. Choose .
4. Choose Edit → Display criteria → All items.
Due to the result of the technical check, the system created a new sub-item in the repair request (10200). This repair item is coupled to a service order that has also been created automatically by the system.
5. Select the first item and choose Repairs.
The result of the technical check has been send to the repair request screen. The decision to execute this operation has been made automatically. (see field RepStatus). The repair item mentioned above and the service order are the result of this decision. The Overview for Repair Request not only displays the Returns but also a new operation Repair.
6. Choose SM Order.
Based on the service order, the devices are repaired. Specifications such as sold-to party, equipment and service product are taken from the repair request.
7. Note the number of the service order (in the field Order in the first line).
8. Choose until the overview tree appears.
April 2001 71
Customer Service (CS) SAP AG
Editing the Service Order
Editing the Service Order
Use
In this step you determine the materials necessary for the repair and also plan the working hours necessary. In the service order, the system calculates the planning costs with this entries.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Service Processing node, choose Order → Service Order → Change.
Transaction Code
IW32
2. Enter the following data:
Field
Data
Order
Noted number of the service order
3. Choose .
4. Choose The Operations tab page.
5. Enter the following data:
Field
Data
Work (in the line for operation 0010)
2
6. Choose the Components tab page.
7. Enter the following data:
Field
Data
Component (in the line of item number 0010)
R-1150
Reqmts.qty. (in the line of item number 0010)
2
Component (in the line of item number 0020)
R-1111
Reqmts.qty. (in the line of item number 0020)
1
8. Choose .
9. Choose until the overview tree appears.
72 April 2001
SAP AG Customer Service (CS)
Processing and confirming the Service Order
Processing and confirming the Service Order
Use
Playing the role of a service technician, you take the materials necessary for the repair. After completing the repair, you confirm the working hours. You post the repaired devices from the blocked stock into the unrestricted-use sales order stock.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Service Processing node, choose Confirmation → Goods Movement → Goods Movement
Transaction Code
MB11
2. Choose To oder...
3. Enter the following data:
Field
Data
Order
Noted number of the service number
4. Choose .
5. If necessary, enter the stroage location 0001 and choose .
6. Choose .
7. Choose .
8. Call up the transaction as follows:
Menu Path
From the Service Processing node, choose Confirmation → Entry → Individual Confirmation (Time)
Transaction Code
IW41
9. Enter the following data:
Field
Data
Order
Noted number of the service order
10. Choose .
11. Enter the following data:
Field
Data
Actual work
2 (default) 12. Choose .
13. Choose until the overview tree appears.
14. Call up the transaction as follows:
April 2001 73
Customer Service (CS) SAP AG
Processing and confirming the Service Order
Menu Path
From the Service Processing node, choose Confirmation → Goods Movement → Goods Movement
Transaction Code
MB11
15. Enter the following data:
Field
Data
Document Date
Current date
Posting date
Current date
Movement type
343
Special stock
E
Plant
1200
Storage location
0001
The movement type 343 and the special stock characteristic trigger a stock transfer of the quantity entered from the blocked stock to the unrestricted-use stock of the respective order.
16. Choose .
17. Enter the following data:
Field
Data
Order
Noted number of the repair request
Item number (in the line Sales Order)
10000
Material (1. line)
R-1001
Quantity
3
18. Choose .
19. Choose .
The system displays the serial number selection.
20. Choose .
The system lists the serial number that are in the blocked stock of the repair request.
21. Choose .
22. Choose .
23. In the dialog box, choose .
24. Choose .
25. Choose until the overview tree appears.
74 April 2001
SAP AG Customer Service (CS)
Processing and confirming the Service Order
April 2001 75
Customer Service (CS) SAP AG
Technically Completing the Service Order
Technically Completing the Service Order
Use
In the service order, you register the completion of the repair. The result is documented on the repair request screen.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Service Processing node, choose Order → Service Order → Change.
Transaction Code
IW32
2. Enter the following data:
Field
Data
Order
Noted number of the service order
3. Choose .
4. Choose .
You posted all devices to the unrestricted-use sales order stock. Thus the system proposes the delivery of the repaired equipment to the customer as the next step. Due to the pre-setting in the repair scheme that is controlled via the schedule, the system automatically creates the sub-item necessary for this operation in the repair request.
5. Choose Continue.
6. In the dialog box, choose .
7. Choose Order → Display.
8. Enter the following data:
Field
Data
Order
Noted number of the service order
9. Choose .
10. To see the document flow, choose .
11. Position your cursor on the line of the sales Order and choose Display document.
12. Choose Edit → Display criteria → All Items.
The item with the number 10300 was created automatically by the system on completing the service order technically. Based on this item, the delivery of the repaired devices to the customer takes place.
13. Choose until the overview tree appears. 76 April 2001
SAP AG Customer Service (CS)
Technically Completing the Service Order
April 2001 77
Customer Service (CS) SAP AG
Delivering the Repaired Piece of Equipment
Delivering the Repaired Piece of Equipment
1. Call up the transaction as follows:
Menu Path
From the Order node, choose Customer Repair → Shipping → Outbound Delivery → Create → Single Document → With Reference to Sales Order.
Transaction Code
VL10N
2. Enter the following data:
Field
Data
Shipping point
1200
Selection date
Current date
Order
Noted number of the repair request
3. Choose .
4. Choose Subsequent functions → Create transfer order.
5. In the dialog box, choose Yes.
6. Enter the following data:
Field
Data
Warehouse number
012
Plant
1200
delivery
Default
Select items
Select (default)
Foreground/background
Background
Adopt pick quantity
2
7. Choose .
Due to the entry in the field Adopt pick quantity the system posts the goods issue directly with this function.
8. Choose until the overview tree appears.
78 April 2001
SAP AG Customer Service (CS)
Creating the Billing Request
Creating the Billing Request
Use
By entering the service order, you create a billing request. With it, the system creates new items in the repair request based on the cost data of the service order. These items are the basis for a later invoice.
1. Enter the following data:
Menu Path
From the Service Processing node, choose Completion → Billing Request → Process Individually
Transaction Code
DP90
Field
Data
Noted number of the service order
Posting date to
Procedure
2. Enter the following data:
Sales document
Default
3. Choose Expenses.
4. Choose Billing Request.
5. In the dialog box, choose Yes.
Due to the settings entered before, the system displays the repair request.
6. Choose Edit → Display criteria → All Items.
7. To display the items with the numbers 10400 to 10600, shift the screen area using the scroll bar, if necessary.
When creating the billing request, the system also created the listed items with the numbers 10400 to 10600. They are transferred to the invoice. These items evaluate the consumed materials or the working hours done. The calculation takes place using service prices entered in the system beforehand.
8. Choose .
9. Choose until the overview tree appears.
April 2001 79
Customer Service (CS) SAP AG
Invoicing the Repair Request
Invoicing the Repair Request
1. Call up the transaction as follows:
Menu Path
From the Service Processing node, choose Completion → Billing Document → Create.
Transaction Code
VF01
2. Enter the following data:
Field
Data
Document
Noted number of the repair request 3. Choose .
The system displays the billing items overview.
4. Choose .
5. Choose until the overview tree appears.
80 April 2001
SAP AG Customer Service (CS)
Settling and Completing the Service Order
Settling and Completing the Service Order
Use
The following function settles the costs of the service order to the repair request. As there will be no further costs, you will also do the business completion for the service order.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Completion node, choose Order Settlement → Settle Individually
Transaction Code
KO88
2. If the Set controlling area dialog box appears, enter the following data and choose :
Field
Data
Controlling area
1000
3. Enter the following data:
Field
Data
Order
Noted number of the SM order
Settlement period
Current month three-digit (e. g. 010 for October)
Fiscal year
Current year
Test run
Deselect
4. Choose .
5. Choose until the overview tree appears.
6. Call up the transaction as follows:
Menu Path
From the Service Processing node, choose Order → Service Order → Change.
Transaction Code
IW32
7. Enter the following data:
Field
Data
Order
Noted number of the service order
8. Choose .
9. Choose Order → Functions → Complete → Complete (business).
10. Choose until the overview tree appears.
April 2001 81
Customer Service (CS) SAP AG
Settling and Completing the Service Order
82 April 2001
SAP AG Customer Service (CS)
Analyzing the Result of the Repair request
Analyzing the Result of the Repair request
Use
The billing request triggered the update of revenues and the service order settlement triggered an update of costs of the main item in the repair request. You display the result of the repair.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Order node, choose Customer Repair → Display.
Transaction Code
VA03
2. Enter the following data:
Field
Data
Order
Noted number of the repair request
3. Choose .
4. Select the first item and choose Environment → Cost report.
The report lists the costs and revenues of the repair. The repair was processed with gains. For the period-end closing, the system finally settles the repair request within the profitability analysis.
5. Choose until the overview tree appears.
April 2001 83
Customer Service (CS) SAP AG
Deactivating the QM Check
Deactivating the QM Check
Use
So that other IDES processes using material R-1001 are not restricted, you will deactivate the QM inspection for this material once again.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Quality Management → Quality Planning → Logistics Master Data → Material → Change.
Transaction Code
MM02
2. Enter the following data:
Field
Data
Material
R-1001
3. Choose Select view(s).
4. Enter the following data:
Field
Data
Quality Management
Select
5. Choose .
6. Enter the following data:
Field
Data
Plant
1200
7. Choose .
8. Choose Insp.setup.
9. Enter the following data:
Field
Data
Active (in the line of InspType 05)
Deselect
10. Choose .
11. Choose .
12. Choose until the overview tree appears.
84 April 2001
SAP AG Customer Service (CS)
Creating a Service Order from a Sales Order
Creating a Service Order from a Sales Order
Purpose
Sales organization 1000 (Germany) of the IDES company sells personal computers and provides a maintenance and repair service for these products. The IDES model company also install networks. If a customer orders the installation of a network, the system determines the network characteristics according to the customers specifications. The system then determines the sales price. The network characteristics also influence the service order that is created simultaneously with the sales order. An employee from the service department of the IDES model company will then execute the network installation at the customer´s based on this service order. The controlling application is able to check the profitability of the individual order, because revenues and costs of the network installation were posted to the sales order.
You can find more information about this process under .
Process Flow
You can find the data for this process under .
1. Entering a Customer Notification and Creating a Service Order
2. Setting an Service Order to In Process
3. Processing the Service Order
6. Analyzing the Cost Report in the Sales Order
8. Analyzing Line Items in the Financial Statement
April 2001 85
Customer Service (CS) SAP AG
Additional Process Information
Additional Process Information
Default Values for the Service Order via the Service Product
The automatic creation of a sales order into a service order requires that plant specifications have been made for the material (service product) of the sales order item which can than be taken into the service order as default values. These specifications contain a link to a general maintenance task list. The general maintenance task list is a work list defining all procedures to be processed. In the call management of the IDES model company we assigned the general maintenance task list NETINST to the service product SM-NETINST. The specifications of this task list are taken into the service order.
The default value determination for a service product is processed via Logistics �� Service Management �� Service processing �� Environment �� Sales and distribution �� Service products.
The general maintenance task list NETINST is defined via Logistics �� Plant Maintenance �� Work Centers �� Task Lists �� general task list (Planning group = NETINST).
Configuration
In the sales order which is the starting point of the process described, the system determines the characteristics of the network installation within the framework of a configuration. The following information assume basic knowledge of variant configuration.
The configuration influences the pricing in the sales order, the activity and component selection in the service order as well as the execution factor of the selected transactions.
When configuring the sales order the system valuates the characteristics of class SM_NETINST. The class comprises six characteristics:
SM_NETWORK_TYPE
Network type
SM_CABLE
Cable type
CH0038
Cable length
SM_CLIENTS
Number of PCs
SM_NET
Network scope
C_OPERATING_SYSTEM
Operating system
Configuration also uses the following two characteristics:
SURCHARGE2
Surcharge
SM_FACTOR
Execution factor
The characteristic SURCHARGE2 links to the table field SDCOM-VCOND. Table SDCOM connects the communication between the module SD (Sales and Distribution) and the variant configuration. The link to the field VCOND (Variant condition) in the table makes the evaluation of the characteristic available for the pricing in the customer order. The automatic pricing determines a surcharge in dependence of this characteristic value.
The characteristic SM_FACTOR links to the table field PLPO-AUFKT. In table PLPO the system saves the activity data of the work list. The field AUFKT contains the respective execution factor.
86 April 2001
SAP AG Customer Service (CS)
Additional Process Information
By using object dependencies the system valuates the characteristic within the framework of the configuration and therefore influences the execution factor of the respective activity in the service order.
Configuration of the Service Product
The service product Network installation is represented by the material master record SM-NETINST. This is a configurable material. Assigned to the configuration profile of this material is the class SM_NETINST. The profile contains two object dependencies. The system derives the scope of network (characteristic SM_NET) from the number of computers in the net (characteristic SM_CLIENTS) via one of the two object dependencies. The other object dependency determines a value for price surcharge (characteristic SURCHARGE2) dependent from the network scope (characteristic SM_NETINST).
Configuration of the General Maintenance Task List
Via default values that are defined for the service product SM_NETINST the system uses the general maintenance task list NETINST (see above) in the service order. The class SM_NETINST has also been assigned to the configuration profile of this general maintenance task list. In the general maintenance task list we determined object dependencies for the individual activities. In the laying cables activity (activity number 0010) the system derives the execution factor from the value of characteristic "cable length" (characteristic CH0038) with the help of which the system determines the work and activity duration in the service order. The execution factor of activity connect PCs (activity 0020) is determined by the number of computers to be installed (characteristic SM_CLIENTS). The activities 0021 to 0023 (Installation of the respective operating systems) are alternative and are selected in the service order due to the specification of the characteristic operating system (characteristic C_OPERATING_SYSTEM). The object dependencies of activity 0030 (install application software) makes its execution factor dependent from the respective operating system. We did not define object dependencies for the last activity.
Configuration of the Material BOM
The general maintenance task list for the network installation (NETINST) contains a link to the assembly SM-NETINST. For material SM-NETINST a BOM exists. This BOM contains three different cable types as components (material number C-1030 to C-1032). Each component has an object dependency assigned to it. The conditions defined there select the components according to the cable type (characteristic SM_CABLE).
In the general maintenance task list NETINST the first activity has three components assigned to it.
April 2001 87
Customer Service (CS) SAP AG
Data Used During This Process
Data Used During This Process
Field
Data
Description
Order type
TA
Sales order
Sales organization
1000
Germany
Distribution channel
14
Distribution channel for end customer
Division
00
Cross-company division
Ordering party
1177
Material
SM-NETINST
Material number for network installation
Technical work center
1177-ADMI
Customer´s technical work center
Evaluation of characteristic Network type
WIN_311
Evaluation of characteristic cable type
COAX
Evaluation of characteristic cable length
100
Evaluation of characteristic Number of PCs
15
Evaluation of characteristic Operating system
WINDOWS
Order type
SM01
Order type of the service order
Working place responsible
PC-SERV
Working center im service order
Plant
1200
Dresden
Controlling area
1000
CO Europe
Operating concern
IDEA
IDES global
88 April 2001
SAP AG Customer Service (CS)
Data Used During This Process
April 2001 89
Customer Service (CS) SAP AG
Entering a Customer Notification and Creating a Service Order
Entering a Customer Notification and Creating a Service Order
Use
The customer orders a network installation. The person responsible enters a sales order and determines the characteristics of the network to be installed according to the customer data within the framework of a configuration. The system derives the prices from these network characteristics. Together with the sales order, the system also creates a service order for the technical service that is to process the installation. This service order is also influenced by the network configuration.
Procedure
1.
Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Environment → Sales and Distribution → Sales → Order → Create
Transaction Code
VA01, VA03
2.
Enter the following data:
Field
Data
Order type
OR
Sales organization
1000
Distribution channel
14
Division
00 3.
Choose .
4.
Enter the following data:
Field
Data
Sold-to party
1177
Purch. order no.
SM-459000
Req.deliv.date
Current date
Material
SM-NETINST
Order quantity
1
5.
Choose .
In the dialog box, choose . 6.
7.
In the dialog box, enter the following data:
Field
Data
FunctLocation
1177-ADMI 90 April 2001
SAP AG Customer Service (CS)
Entering a Customer Notification and Creating a Service Order
The functional location represents the place where the installation will be processed for the customer. The entry made here will be copied into the service order.
8.
Choose .
You can see a net value of 2045 EUR.
9.
In the Characteristic Value Assignment screen area, choose the F4 input help for each characteristic. The system lists default attributes of each characteristic in a window. These can be chosen. For other characteristics you have to enter a value yourself in the window. After making your selection in the window, choose . Choose the characteristics as follows:
Field
Data
Network type
WIN_311
Type of Cable
COAX
Cable Length
100 (enter)
No. of PCs
15 (enter)
Operating system
Windows
10.
Choose .
You can see that the system has derived a scope of network (10 to 20 PCs) from the number of PCs to be installed.
Due to the characteristic valuation, there is a new net value of 2812 EUR.
11.
12.
Choose Conditions... .
The system displays an overview of the resulting variant conditions.
The attribute A (10 to 20 PCs) of the scope of network is linked to a surcharge of 767EUR for each network installation.
Choose . 13.
Choose . 14.
Choose 15.
16.
17.
18.
Note the order number.
Choose Sales document → Display.
Enter the following data.
Field
Data
Order
Your order number
19.
Choose Item Overview.
Select the item, then choose . 20.
April 2001 91
Customer Service (CS) SAP AG
Entering a Customer Notification and Creating a Service Order
Select the schedule line, then choose . 21.
22.
Choose the Procurement tab page.
In the Customer Service screen area, the system displays the order number issued by the system for the service order.
23.
24.
Note this order number.
Choose until the overview tree appears.
92 April 2001
SAP AG Customer Service (CS)
Setting an Service Order to In Process
Setting an Service Order to In Process
Use
In this process step you play the role of an employee in the technical service of the IDES AG and have the system list service orders that have not yet been processed. You determine the employee responsible for the processing of the service order created in the previous step. Afterwards you set the service order to in process.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Service Processing node, choose Order → Service Order → Service Order List → Change
Transaction Code
IW72
2. Enter the following data:
Field
Data
Order status outstanding
Select
Order type
SM01
MainWorkCenter
PC-SERV
Period
Current date
Period to
Delete default entry
Entered by (in the section general data/administrative data)
Your user name
Created on
Current date
3. Choose .
If several service orders correspond to these selection criteria, the Change Service Orders: List of Orders screen appears. In this case, select the entry with your noted service order number, then choose .
4. In the Person responsible screen area, enter the following data:
Field
Data
Person res
1523 5. Choose .
6. Choose .
7. In the dialog box, select W/o print.
8. Choose .
April 2001 93
Customer Service (CS) SAP AG
Setting an Service Order to In Process
9. Choose until the overview tree appears.
94 April 2001
SAP AG Customer Service (CS)
Processing the Service Order
Processing the Service Order
Use
In this process, you play the role of a service technician who is responsible for the order processing. At first inform yourself which orders have to be processed by you.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Service Processing node, choose Order → Service Order → Service Order List → Display
Tranasaction Code
IW73
2. Enter the following data:
Field
Data
Order status In process
Select
Order type
SM01
Main work center
PC-SERV
Period
Current date
Period to
Delete the default entry
Partner
Person responsible (F4 help) / 1523
Entered by (in the section general data/administrative data)
Your user name
Created on
Today's date
3. Choose .
If several service orders correspond to these selection criteria, the Display Service Orders: List of Orders screen appears. In this case, select the entry with your noted service order number, then choose .
4. Choose until the overview tree appears.
5. Call up the transaction as follows:
Menu Path
From the Service Procession node, choose Confirmation → Goods Movement → Goods Movement
Transaction Code
MB11
6. Enter the following data:
Field
Data
Document date
Current date
April 2001 95
Customer Service (CS) SAP AG
Processing the Service Order
Posting date
Current date
Plant
1200
7. Choose To Order... .
8. Enter the following data:
Field
Data
Order
Your order number
9. Choose .
The system defaults the quantity defined in the order.
10. Choose .
If the system requests a storage location, enter 0001 in the field SLoc.
The system issues a document number for the goods movement. All costs incurred by the goods withdrawal are posted to the service order.
11. Choose until the overview tree appears.
12. Call up the transaction as follows:
Menu Path
From the Service Procession node, choose Confirmation → Entry → Individual Confirmation (Time)
Transaction Code
IW41
13. Enter the following data:
Field
Data
Order
Service order number
14. Choose .
15. In the Overview screen area, choose , then choose Actual Data.
16. Choose until a message informs you that the last operation has been reached.
17. Enter the following data:
Field
Data
Actual Work
3
Choose .
Due to the confirmed data, the system posts the personnel costs to the service order.
18. Choose until the overview tree appears.
96 April 2001
SAP AG Customer Service (CS)
Processing the Service Order
April 2001 97
Customer Service (CS) SAP AG
Settling the Service Order
Settling the Service Order
Use
After the service order has been completed, it has to be settled. With this order settlement, the system transfers the accumulated costs to the relevant recipient. The recipient will be the sales order that triggered the service order.
Procedure
1. Call up the transaction as follows:
Menu Path
Fom the Completion node, choose Order Settlement → Single
Transaction Code
KO88
2. If the controlling area has not yet been determined, the system displays the Set Controlling Area dialog-box. Enter the following data and choose :
Field
Data
Controlling area
1000
3. Enter the following data (retain the other default values):
Field
Data
Order
Service order nummer
Settlement period
Current period (three digit; e. g. 003)
Test run
Deselect
4. Choose .
5. Choose until the overview tree appears.
98 April 2001
SAP AG Customer Service (CS)
Invoicing the Sales Order
Invoicing the Sales Order
Use
After completion of the network installation, you invoice the service delivered to the customer.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Environment node, choose Sales and Distribution → Billing Document → Billing Document → Create.
Transaction Code
VF01
2. Enter the following data:
Field
Data
Document
Your sales order number 3. Choose .
The system informs you that the invoice document has been added.
4. Choose until the overview tree appears.
April 2001 99
Customer Service (CS) SAP AG
Analyzing the Cost Report in the Sales Order
Analyzing the Cost Report in the Sales Order
Use
When you settle the service order, the costs are transferred to the sales order. When you created the billing document, the system also updated the revenues on the sales order. You can now analyze the result on the individual sales order.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Environment node, choose Sales and Distribution → Sales → Order → Display.
Transaction Code
VA03
2. Enter the following data:
Field
Data
Order
Your sales order number
3. Choose .
4. Choose Environment → Cost Report.
The cost report displays costs of material consumption and personnel costs that occurred when you executed the service order derived from the sales order item. You also see the net sales incurred due to the sales order invoicing compared to the costs.
5. Choose .
6. Choose until the overview tree appears.
100 April 2001
SAP AG Customer Service (CS)
Settling the Sales Order
Settling the Sales Order
Use
The sales order for the network installation whas been executed and invoiced. The costs and revenues are now transferred to the financial statement.
Procedure
1. Call up the transaction as follows:
Menu Path
From the Sales node, choose Order → Subsequent Functions → Settlement.
Transaction Code
VA88
2. Enter the following data:
Field
Data
Sales organization
1000
Sales document
Your sales order number
Settlement period
Current period (three digits: such as 003)
Fiscal year
Current year
Test run
Deselect
3. Choose .
The sales order item settles your result in the profitability segment of the financial statement.
4. Choose until the overview tree appears.
April 2001 101
Customer Service (CS) SAP AG
Analyzing Line Items in the Financial Statement
Analyzing Line Items in the Financial Statement
Use
The costs and revenues were forwarded to the financial statement when you settled the sales order. The data are recorded via a line item in the financial statement.
The information system of the financial statement lets you evaluate the dataset created due to the lines items. In this process step you analyze specific line items.
Procedure
5. Call up the transaction as follows:
Menu Path
Accounting → Controlling → Profitability Analysis → Environment → Set Operating Concern
Transaction Code
KEBC
6. Enter the following data:
Field
Data
Operating concern
IDEA
Costing-based
Select
7. Choose .
8. Call up the transaction as follows:
Menu Path
From the Profitability Analysis node, choose Actual Postings → Display Line Items.
Transaction Code
KE24
9. Enter the following data:
Field
Data
Record Type
C
Period/year
Current period (three digits: such as 004.1998)
Date created
Current date
Entered by
Your user name 10. Choose .
11. Position your cursor on the line of currency type B0 (field Ct.), then choose Profitability segment.
The system displays the value characteristics. These were used to post the line item in the financial statement. 102 April 2001
SAP AG Customer Service (CS)
Analyzing Line Items in the Financial Statement
12. Choose Continue.
13. Position your cursor on the line of currency type B0 (profitability segment), then choose .
14. Choose the Value fields tab page.
For the value characteristics mentioned above, the system posted revenues and the average delivered price to the financial statement.
To scroll through the list of value fields, choose if necessary.
15. Choose until the overview tree appears.
April 2001 103
Customer Service (CS) SAP AG
Processing Telephone Calls in a Call Center
Processing Telephone Calls in a Call Center
Purpose
The IDES AG has set up a call center for the areas Sales and Distribution and Service Management. Incoming customer calls are routed to the call center employees via Computer Telephony Integration (CTI). The call center makes it possible to execute a variety of telephone operations such as, receiving calls, forwarding calls and callbacks. The call center employees can use call processing to call up the R/3 functions required for the specific Sales or Service area (for example, creating a service notification).
Two variants exist for this: Variant A displays the call center with Computer Telephony Integration. The incoming customer call is simulated. Variant B displays the call center without Computer Telephony Integration.
The first two preparatory steps required to run this IDES process are carried out just once by the system administrator when they set up the call center.
Process Flow
You can find the data for this process under .
1. Preparations - Assigning the CIC Profile
2. Preparations - Defining the Work Center
3. Processing a Customer Call (Variant A)
4. Processing a Customer Call (Variant B)
104 April 2001
SAP AG Customer Service (CS)
Data Used During This Process
Data Used During This Process
Field
Data
Description
User
P00001990
R/3 User ID
Organizational Unit
50014697
Call center
Telephony server
NOSERV
Server simulation
ANI
040-567-712
Telephone number of the caller
Equipment
10003562
Personal computer
April 2001 105
Customer Service (CS) SAP AG
Preparations: Assigning the CIC Profile
Preparations: Assigning the CIC Profile
Use
The organizational structure of IDES AG is defined in organization management. The call center is an organizational unit within this organizational structure. Positions are assigned to the call center. The position is the individual assignment of an employee to the call center.
Call centers can be characterized in different ways. You define the relevant characteristic in a CIC-Profile (CIC = Customer Interaction Center). You assign the CIC profile either at organizational unit level, or at position level. In this demo, you assign the profile to the call center (organizational unit). This means that all employees belonging to this call center work using this profile.
The R/3 user ID with which you log on to the system for this process has been assigned the personnel number 1990. The employee with personnel number 1990 belongs to the organizational unit Call center.
Procedure
1. Log on to the IDES system with user ID P00001990 (password: IDES).
2. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Customer Interaction Center → Administration → CIC Structure → Organizational Structure → Change
Transaction Code
PPOM, PP01
3. If the Organization and Staffing (Workflow) Change screen appears, choose Settings → Maintenance interface
4. Enter the following data:
Field
Data
Organizational unit
50014697
5. Choose .
6. Choose Staff assignments.
7. Choose View → Key on.
8. Choose View → Assignments → User on.
9. Position your cursor on Call Center, then choose .
10. Choose View → Color legend.
You can see that a position belongs to the call center. In this demo, the position is assigned to personnel number 1990 - Marek Czarny, in the personnel administration department. This employee has the R/3 User ID P00001990. It is also possible to assign an R/3 User ID directly to the position.
11. In the Legend dialog box, choose .
106 April 2001
SAP AG Customer Service (CS)
Preparations: Assigning the CIC Profile
12. Position your cursor on Call center, then choose Goto → Object description.
13. Choose the Active tab page.
14. Select CIC Profile.
If necessary, use the scroll bar until you see the infotype name CIC Profile.
15. Choose .
The following entry depends on the type of variant you have selected.
Start Variant A (Simulation of Computer Telephony Integration)
16. Enter the following data:
Field
Data
CIC Profile ID
00000002
End Variant A (Simulation of Computer Telephony Integration)
17. Continue with No.19.
Start Variant B (Without Computer Telephony Integration):
18. Enter the following data:
Field
Data
CIC Profile ID
00000001
End Variant B (Without Computer Telephony Integration):
19. Choose .
20. Choose until the overview tree appears.
April 2001 107
Customer Service (CS) SAP AG
Preparation: Defining the Work Center
Preparation: Defining the Work Center
Use
The work center settings summarize the attributes of the PC and telephone. SAPphone can therefore assume a constant relationship between these two components. The assignment of the user ID to the work center, however, is made dynamically, that is, it occurs each time the user logs on to a PC.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Customer Interaction Center → Administration → Agent → Settings
Transaction Code
SPHA
2. Choose Work center.
3. Enter the following data:
Field
Data
Telephone number
12345
Telephony server
NOSERV
User
P00001990
4. Choose .
5. If the Copy Data dialog box appears, choose Yes.
6. The Delete Old Work Center may also appear. Choose Yes.
If you are running this demo at a different PC, this process step deletes the work center data that you have just created. For this reason, the demo sequence ensures that the work center data are checked, and recreated, if required, before you call up the call center.
7. Choose until the overview tree appears.
108 April 2001
SAP AG Customer Service (CS)
Processing a Customer Call (Variant A)
Processing a Customer Call (Variant A)
Use
You play the role of an employee in a call center of the IDES AG. You take a call from a customer. The customer informs you about a defect of an equipment. On the basis of this information, you create a service notification.
In this process, we simulate Computer Telephony Integration (CTI). During this simulation session, dialog boxes appear in which you can make technical entries for test purposes. To skip the dialog boxes, choose .Of course, these dialog boxes do not appear when you are working in a productive system.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Customer Interaction Center → Front Office → Front Office
Transaction Code
CICO
2. In the subsequent technical dialog boxes, choose , until the Customer Interaction Center screen appears.
We now simulate an incoming customer call in the Call center.
3. Choose Inwait.
The wait mode informs the system that the agent is ready to take incoming calls.
4. In the dialog box, choose .
5. Enter the following data:
Field
Data
Call status
Ringing
ANI
040-567-712
(The telephone number of the calling communication partner)
DNIS
0800-123456
(Telephone number dialed by the communication partner) 6. Choose .
The system responds to the new call and displays the incoming telephone number. The system uses the ANI function (Automatic Number Identification) to identify the name of the caller on the customer side.
April 2001 109
Customer Service (CS) SAP AG
Processing a Customer Call (Variant A)
The system also displays the service number dialed by the customer and an accompanying description.
7. Choose the Search/Display tab page.
You can see that the caller is an employee of the company Hitech AG.
8. Choose the Callstate tab page.
9. Position your cursor on the caller row, then choose Answer.
You are now connected with the caller.
10. Choose the Search/Display tab page.
11. Choose .
12. Enter the following data:
Field
Data
Customer number
1171 (defaulted)
Sales organization
1000 (defaulted)
Distribution channel
Not selected
Division
Not selected
13. Choose .
The system lists information for the customer.
14. Choose until the Customer Interaction Center screen appears.
15. Choose the Business Data tab page.
You see the information for this business transaction (customer and contact person).
The customer reports a defective piece of equipment. You enter a service notification.
16. Choose the Service tab page.
17. Choose .
The system defaults the notification type, the customer number of the sold-to-party is taken from the business data display.
18. Enter the following data:
Field
Data
Notification (in the first line)
Problem with hard disc
Equipment
10003562
Object part (1st field)
PC
Object part (2nd field)
5
Damage (1st field)
PC
110 April 2001
SAP AG Customer Service (CS)
Processing a Customer Call (Variant A)
Damage (2nd field)
E
19. Choose .
20. Choose .
21. Choose the Business Data tab page.
The system displays the issued notification number.
22. Choose Edit → End call.
23. Choose until the overview tree appears.
April 2001 111
Customer Service (CS) SAP AG
Processing a Customer Call (Variant B)
Processing a Customer Call (Variant B)
Use
You play the role of an employee in a call center of the IDES AG, where you take a call from a customer. The customer informs you about a defect of an equipment. On the basis of this information, you create a service notification.
Procedure
8. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Customer Interaction Center → Front Office → Front Office
Transaction Code
CICO
You take a call from a Hitech AG customer.
9. Enter the following data:
Field
Data
The right-hand entry field of the Customer line
Hitech
10. Choose .
The system displays customer number 1171.
11. In the Contact Person line, choose the possible entries pushbutton.
12. In the Hit List dialog box, position your cursor on a contact person, then choose .
13. In the middle of the screen, choose .
Your entries are now transferred to the business data (upper screen area), where you can use them for additional processing in the R/3 System (for example, creating a service notification.
14. Choose .
15. Enter the following data:
Field
Data
Customer number
1171 (defaulted)
Sales organization
1000 (defaulted)
Distribution channel
Not selected
Division
Not selected
16. Choose .
The system lists information for the customer.
17. Choose until the Customer Interaction Center screen appears.
112 April 2001
SAP AG Customer Service (CS)
Processing a Customer Call (Variant B)
The customer reports a defective piece of equipment. You enter a service notification.
18. Choose the Service tab page.
19. Choose .
The system defaults the notification type, the customer number of the sold-to-party is taken from the business data display.
20. Enter the following data:
Field
Data
Equipment
10003562
Object part (1st field)
PC
Object part (2nd field)
5
Damage (1st field)
PC
Damage (2nd field)
E
21. Choose .
22. Choose .
The system displays the issued notification number.
23. Choose End contact.
24. Choose until the overview tree appears.
April 2001 113
Customer Service (CS) SAP AG
Service Contracts
Service Contracts
Processing Service Contracts with Periodic Billing
Service Processing and Resource-Related Billing with Service Contracts
Spare Parts Delivery with a Service Contract
114 April 2001
SAP AG Customer Service (CS)
Processing Service Contracts with Periodic Billing
Processing Service Contracts with Periodic Billing
Purpose
This process shows you how to create and process service contracts for customer equipment. It contains periodic billing for service contracts and a link to a further process containing resource-related billing.
Prerequisites
The process begins with the delivery of a personal computer to the customer. Once delivered, an equipment master record is created. The customer would like to conclude a service contract for the equipment. If the customer desires, configurable or preconfigured service packages can be used in the service contract. It includes special price agreements for the materials that can be used in subsequent service measures. These price agreements are automatically taken into account in resource-related billing (see the scenario Service Processing and Resource-Related Billing with Service Contracts ). The service contract also contains the standard charge billed each month. A settlement is drawn up for the monthly charge, and the revenues (as well as any costs) are settled to Profitability Analysis (CO-PA).
The scenario can be performed separately or together with the scenario Service Processing and Resource-Related Billing with Service Contracts .
Process Flow
You can find the data for this process under .
1. Creating and Delivering Sales Orders
2. Creating the Equipment Master Record
3. Creating Service Contracts for the Plant Maintenance of Customer Equipment
4. Maintaining Price Agreements in the Service Contract
5. Service Processing and Resource-Related Billing
6. Performing Periodic Billing Document
7. Settlement of Service Contracts
8. Displaying Line Items in Profitability Analysis
9. Displaying a CS Report in Profitability Analysis
April 2001 115
Customer Service (CS) SAP AG
Data Used During This Process
Data Used During This Process
Field
Data
Description
Plant
1200
Dresden
Company code
1000
IDES AG
Business area
8000
External Services
Main work center
PC-SERVS/1200
Service contract type
WV
Service and maintenance
Material numbers
R-1001 R-1111 R-1120
Maxitec-R3100 PC Motherboard M-3100 Cable with earthed plug
Service materials
REPAIR SERVICE PC_SERVICE_CONF PC_SERVICE_A
Sold-to party
1032
Inst.f. Environmental Research
Sales organization
1000
Germany Frankfurt
Distribution channel
14
Service
Division
00
Cross-division
116 April 2001
SAP AG Customer Service (CS)
Creating and Delivering Sales Orders
Creating and Delivering Sales Orders
1. Call up the transaction as follows:
Menu Path
Logistics → Sales and Distribution → Sales → Order → Create
Transaction Code
VA01
2. Enter the following data:
Field
Data
Order type
TA
Sales organization
1000
Distribution channel
10
Division
00
3. Choose .
4. Enter the following data:
Field
Data
Sold-to party
1032
PO number
SM-329800
Req. deliv. date
Today's date + 7 working days
Material
R-1001
Order quantity
1
5. Choose .
The system produces a BOM explosion. This generates additional items which serve as an explanation.
6. Choose the Shipping tab page, and note the material availability date of the first item.
7. Choose .
8. Make a note of the sales order number.
9. Choose until the overview tree appears.
10. In the dialog box, choose No.
11. Call up the transaction as follows:
Menu Path
Logistics → Sales and Distribution → Shipping and Transportation → Outbound Delivery → Create → Single Document → With Reference to Sales Order
Transaction Code
VL01N, LT03
12. Enter the following data:
April 2001 117
Customer Service (CS) SAP AG
Creating and Delivering Sales Orders
Field
Data
Shipping point
1200
Selection date
e.g. today's date + 1 month
Order
No. of your customer order
From item
Empty
To item
Empty
13. Choose .
You now see the overview screen for the delivery document.
14. Select the first item, then choose Extras → Serial numbers.
15. Choose .
16. In the Serial number selection screen area, enter the following data:
Field
Data
Plant
1200
Storage location
0001
17. Choose .
The system produces a list of serial numbers occurring in the specified plant and storage location.
18. Select the first entry in the list, then choose .
19. Make a note of the selected serial number.
20. In the dialog box, choose .
21. Choose Subsequent functions → Create transfer order.
22. In the dialog box, choose Yes.
23. Enter the following data:
Field
Data
Warehouse number
012
Plant
1200
Delivery
Proposed by the system
Foreground/Background
Background
Adopt picking quantity
2
24. Choose .
The system creates a transfer order for picking the delivery quantities. The option 2 (Adopt picking quantity) means that the goods issue is posted immediately for that delivery.
25. Choose until the overview tree appears. 118 April 2001
SAP AG Customer Service (CS)
Creating and Delivering Sales Orders
April 2001 119
Customer Service (CS) SAP AG
Creating the Equipment Master Record
Creating the Equipment Master Record
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Management of Technical Objects → Serial Numbers → List Editing → Change
Transaction Code
IQ08, IQ02
2. Enter the following data:
Field
Data
Material
R-1001
Partner (1st field)
Sold-to-party
Partner (2nd field)
1032
3. Choose .
4. Select the line for your serial number, then choose .
5. Choose Equipment view.
6. Choose the Sales and Distribution tab page.
7. Enter the following data:
Field
Data
Sales org.
1000
Distribution channel
14
Division
00
8. Choose the Organization tab page.
9. Enter the following data:
Field
Data
Company code
1000
Business area
8000
Planning plant
1200
Planning group
201
Main work center
PC-SERVS/1200
10. Choose the Ser.data tab page.
11. If any warning messages appear, choose .
12. Note the equipment number.
13. Choose .
14. Choose until the overview tree appears. 120 April 2001
SAP AG Customer Service (CS)
Creating the Equipment Master Record
April 2001 121
Customer Service (CS) SAP AG
Creating Service Contracts for Maintenance of Customer Equipment
Creating Service Contracts for Maintenance of Customer Equipment
You now see how to create service contracts for customer equipment. You can choose whether you wish to use nonconfigurable, configurable or preconfigured service packages in your service contract.
Choose one of the three possible options:
Creating Service Contracts (Nonconfigurable)
Creating Service Contracts with a Configurable Service Package
Creating Service Contracts with a Preconfigured Service Package
122 April 2001
SAP AG Customer Service (CS)
Maintaining Price Agreements in the Service Contract
Maintaining Price Agreements in the Service Contract
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Agreements → Contracts → Contract → Change
Transaction Code
VA42
2. Enter the following data:
Field
Data
Contract
Your service contract number
3. Choose .
4. Select your item, then choose Price agreements.
5. Choose .
6. In the dialog box, enter the following data:
Field
Data
Condition type
ZZDC (Item Discount Contract)
7. Choose .
8. Enter the following data:
Field
Data
Material
R-1120
Rate
10
Material
R-1111
Rate
15
9. Choose .
10. Choose .
11. Choose again.
12. Choose until the overview tree appears.
April 2001 123
Customer Service (CS) SAP AG
Service Processing and Resource-Related Billing (optional)
Service Processing and Resource-Related Billing (optional)
This step enables you to process a complete service case for the customer equipment relating to the service contract created previously. Since this is an optional enhancement for contract processing itself, you can also proceed with the following step.
If you wish to process a service notification and a service order relating to your contract, select the following process:
Service Processing and Resource-Related Billing with Service Contracts
124 April 2001
SAP AG Customer Service (CS)
Performing Periodic Billing Document
Performing Periodic Billing Document
Use
In this step, you bill the monthly amounts that are due according to the billing plan for the service contract.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Agreements → Contracts → Contract → Display
Transaction Code
VA43
2. Enter the following data:
Field
Data
Contract
Your service contract number
3. Choose .
4. Select your service item, then choose .
The basic price for the service (condition type PPSV) and where applicable the surcharges/deductions are used to calculate the net price (Target: net value for item). This net price is then billed each month.
Check the monthly standard price for your service (condition type PPSV).
5. Choose .
6. Select your service item, then choose Billing plan.
Check the rules and items of the billing plan. Note how the billing amount for the first and last month is confined to the billing horizon.
Only the billing items in the selected horizon are displayed. Depending on the setting, the billing date or billing value of the last month of validity for your contract is not displayed.
7. Choose , until the overview tree appears.
8. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Environment → Sales and Distribution → Billing Document → Billing Document → Process Billing Due List
Transaction Code
VF04, VF01
9. Enter the following data:
Field
Data April 2001 125
Customer Service (CS) SAP AG
Performing Periodic Billing Document
Billing date until
Last day of current month
Billing type
F2
Sold-to party
1032
Order-related
Select
10. Choose DisplayBill.list.
11. Choose .
12. Select the line containing your service contract and choose Individual billing document.
13. Choose .
14. Choose until the overview tree appears.
15. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Agreements → Contracts → Contract → Display
Transaction Code
VA43
16. Enter the following data:
Field
Data
Contract
Your service contract number
17. Choose .
18. Select your service item, then choose Billing plan.
The status (column BillSt in the table) of the billing item has changed from status A (not billed) to status C (completely processed).
19. Choose until the overview tree appears.
126 April 2001
SAP AG Customer Service (CS)
Settlement of Service Contracts
Settlement of Service Contracts
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Agreements → Contracts → Contract → Display
Transaction Code
VA43
2. Enter the following data:
Field
Data
Contract
Your service contract number
3. Choose .
4. To check the actual sales revenue for your service contract, choose Environment → Cost report.
If you have settled a service order to your service contract (using, for example, the process Service Processing and Resource-Related Billing with Service Contracts ), then you will also find the costs and revenues for that service order in the cost report. The planned revenues that are produced from the validity period of the billing plan are compared with the actual revenues obtained so far.
5. Choose until the overview tree appears.
6. Call up the transaction as follows:
Menu Path
From the Contracts node choose Contract → Follow-on functions → Settlement
Transaction Code
VA88
7. If the Set Controlling Area dialog box appears, enter the following data and choose :
Field
Data
Controlling area
1000
8. Enter the following data:
Field
Data
Sales Organization
1000
Sales document
No. of your service contract
Settlement period
Current period (current month)
Fiscal year
Current fiscal year
Test run
Deselect
9. Choose .
You see a detailed list of the settled amounts.
April 2001 127
Customer Service (CS) SAP AG
Settlement of Service Contracts
10. Choose until the overview tree appears.
11. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Agreements → Contracts → Contract → Display
Transaction Code
VA43
12. Enter the following data:
Field
Data
Contract
Your service contract number
13. Choose .
14. Choose Environment → Cost report.
You can now check that the contract has been credited by the order settlement and that the total of debits and credits is now zero.
15. Choose until the overview tree appears.
The operative service process is complete after settlement. Both steps deal with the transaction from the Profitability Analysis view CO-PA). Firstly, you deal with the line item generated during settlement. You then perform a report, which analyzes all present profitability data relating to services. The values for the present process flow into this report.
128 April 2001
SAP AG Customer Service (CS)
Creating Service Contracts (Nonconfigurable)
Creating Service Contracts (Nonconfigurable)
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Agreements → Contracts → Contract → Create
Transaction Code
VA41
2. Enter the following data:
Field
Data
Contract type
WV
Sales organization
1000
Distribution channel
14
Division
00
3. Choose .
4. Enter the following data:
Field
Data
Sold-to party
1032
PO number
e.g. service/001
Contract end date
Contract start date + 2 years
Material
REPAIR_SERVICE
Target quantity
1
5. Choose .
6. To skip the warning message regarding the end date, choose .
7. In the dialog box, choose Yes.
8. Select your item.
9. Choose Extras → Technical objects.
10. Enter the following data:
Field
Data
Equipment
Your equipment number 11. Choose .
12. Choose .
13. Choose the Item overview tab page.
14. Select your service item, then choose Billing plan.
Verify the entries in the billing plan. Note that the billing document value for the first and last month is delimited.
April 2001 129
Customer Service (CS) SAP AG
Creating Service Contracts (Nonconfigurable)
Only the billing items in the selected horizon are displayed. Depending on the setting, the billing date or billing value of the last month of validity for your contract is not displayed.
15. Choose .
16. Choose .
17. Make a note of the contract number.
18. Choose until the overview tree appears.
19. In the dialog box, choose No.
To continue processing your service contract in the next process step, choose: Maintaining the Price Agreements in the Service Contract
130 April 2001
SAP AG Customer Service (CS)
Creating Service Contracts with a Configurable Service Package
Creating Service Contracts with a Configurable Service Package
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Agreements → Contracts → Contract → Create
Transaction Code
VA41
2. Enter the following data:
Field
Data
Contract type
WV
Sales organization
1000
Distribution channel
14
Division
00
3. Choose .
4. Enter the following data:
Field
Data
Sold-to party
1032
PO number
e.g. service/001
Contract end date
Defaulted
Material
PC_SERVICE_CONF
Target quantity
1
5. Choose .
6. Choose Continue.
7. Enter the following data:
Field
Data
Response profile
EPRESS
Service profile
EVERYDAY
Travel zone
50 (less than 50 km)
Repair location
Customer location
8. Choose .
9. Choose .
10. Select the item. Choose Extras → Technical objects.
11. Enter the following data:
April 2001 131
Customer Service (CS) SAP AG
Creating Service Contracts with a Configurable Service Package
Field
Data
Equipment
Your equipment number 12. Choose .
13. Choose .
14. Select your service item, then choose Billing plan.
Verify the entries in the billing plan. Note that the billing document value for the first and last month is delimited.
Only the billing items in the selected horizon are displayed. Depending on the setting, the billing date or billing value of the last month of validity for your contract is not displayed.
15. To quit the billing plan, choose .
16. Choose .
17. Note the number of the contract.
18. Choose until the overview tree appears.
Continue processing your service contract with Maintaining Price Agreements in the Service Contract .
132 April 2001
SAP AG Customer Service (CS)
Creating Service Contracts with a Preconfigured Service Package
Creating Service Contracts with a Preconfigured Service Package
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Agreements → Contracts → Contract → Create
Transaction Code
VA41, VA45
2. Enter the following data:
Field
Data
Contract type
WV
Sales organization
1000
Distribution channel
14
Division
00
3. Choose .
4. Enter the following data:
Field
Data
Sold-to party
1032
PO number
e.g. service/001
Contract end
Contract start date + 2 years
Material
PC_SERVICE_A
Target quantity
1
5. Choose .
6. To skip any warning messages regarding the end date, choose .
7. In the dialog box, choose Yes.
8. Select your item.
9. To display the characteristic value assignment predefined for this service material, choose .
10. Choose .
11. Select your item. Choose Extras → Technical objects.
12. Enter the following data:
Field
Data
Equipment
quoted equipment number 13. Choose .
April 2001 133
Customer Service (CS) SAP AG
Creating Service Contracts with a Preconfigured Service Package
14. Choose .
15. Choose Contracts and check the contract duration.
16. Choose .
17. Select your service item, then choose Billing plan.
18. Verify the entries in the billing plan. Note that the billing document value for the first and last month is delimited.
Only the billing items in the selected horizon are displayed. Depending on the setting, the billing date or billing value of the last month of validity for your contract is not displayed.
19. Choose .
20. Choose .
21. Make a note of the contract number.
22. Choose until the overview tree appears.
23. In the dialog box, choose No.
Continue processing your service contract with Maintaining Price Agreements in the Service Contract .
134 April 2001
SAP AG Customer Service (CS)
Displaying Line Items in Profitability Analysis
Displaying Line Items in Profitability Analysis
Use
The costs and revenues are attained under record type C (order and project settlement) in Profitability Analysis through the settlement of the service contract.
Procedure
1. Call up the transaction as follows:
Menu Path
Accounting → Controlling → Profitability Analysis → Information System → Display Line Item List → Actual
Transaction Code
KE24
If you are processing an operating concern in this session for the first time, the Set Operating Concern dialog box appears.
2. Enter the following data:
Field
Data
Operating concern
IDEA
Type of profitability analysis
Costing-based
3. Choose .
This dialog box is only displayed once per session. Once you have made your selection, the system assumes that you will only work in this operating concern and type in this session.
4. Enter the following data:
Field
Data
Currency type
B0
Date created
Todays date
Entered by
Your user name
5. Choose .
6. Choose .
You can see that the item with record type C has been posted from service management to CO-PA through settlement.
7. Double-click on this line item.
You now see, for example, the customer name and the organizational units.
The item reference is actually the material number for the service product. You see the corresponding assignments to a plant, profit center level, and so on.
April 2001 135
Customer Service (CS) SAP AG
Displaying Line Items in Profitability Analysis
Here you can see all the characteristics that can be analyzed in Profitability Analysis. The values for these characteristics were derived from the customer and material master records, the SD partner functions (such as the sales representative), or from CO-PA specific characteristics.
Note that the list of characteristic values is displayed over several screens. To scroll through the characteristics, choose .
8. Choose the Value fields tab page.
9. To scroll down, choose .
You can see detailed information about the order and billed quantities, revenues, discounts, and detailed product cost components that were derived from SD and CO-PC. Note that the list of value fields spans several screens.
Revenue is made up of the total from contract billing and the total from the billing of the service order assigned to the contract (although the latter is only involved if you integrated the process Service Processing and Resource-Related Billing with Service Contracts into the current process).
Customer discount is calculated from the total of sales deductions posted during contract billing or during the billing of the service order assigned to the contract (although the latter is only involved if you integrated the process Service Processing and Resource-Related Billing with Service Contracts into the current process).
Sales commission is calculated by valuating anticipated costs from Profitability Analysis.
Material usage is made up of the costs that were generated through the use of materials for the service order (although only if you integrated the process Service Processing and Resource-Related Billing with Service Contracts into the current process).
Maintenance costs represent any service technician charges (although only if you integrated the process Service Processing and Resource-Related Billing with Service Contracts into the current process).
10. Choose until the overview tree appears.
136 April 2001
SAP AG Customer Service (CS)
Displaying a CS Report in Profitability Analysis
Displaying a CS Report in Profitability Analysis
Use
The report IDES-090 CS reporting uses different accounts receivable and service products to demonstrate how the reporting procedure for service management can be structured. The costs and revenues generated in the previous steps have been prepared for reporting and evaluated as key figures.
Procedure
1. Call up the transaction as follows:
Menu Path
Accounting → Controlling → Profitability Analysis → Information System → Execute Report
Transaction Code
KE30
2. Select the report IDES-090 and choose .
3. Enter the following data:
Field
Data
Fiscal year
Current fiscal year
From period
1
To period
Current period 4. Choose .
You see the basic screen of the report. In the report header, you see the dimensions defined for this report. Sales organization 1000, Germany, Frankfurt and distribution channel 14 Service.
Beneath the report header, you find the navigation field which enables you to navigate through the individual service products. The key figures include revenues, sales deductions, costs and the resultant contribution margins which are displayed in the additional columns and are accumulated for the individual accounts receivable.
In the fourth column, you see the customer Institute for Environmental Research (customer number 1032) for which you have created the service contract (and service order, if applicable).
5. To access the product level, choose Product in the Navigation field.
6. If the Drilldown: Callup Documentation on Hotspots screen appears, choose .
7. Choose next to the field Product.
8. Select the product(s) which you used in the previous process.
The totals of the value fields for the customer Institute for Environmental Research are obtained from the line items showed previously as well as from any other postings.
9. Choose .
The characteristic Product now appears in a different color.
April 2001 137
Customer Service (CS) SAP AG
Displaying a CS Report in Profitability Analysis
10. To call up the drilldown list choose Product.
For each individual key figure, you obtain an overview of all products in sales organization 1000 and distribution channel 14 and of the customers who have generated revenues or costs for these products. It is now possible to perform a direct comparison of all service products. The overall result is displayed in the last line.
11. To view other key figures for this listing, choose .
For more information on navigation within a report, see Performing Defined Reports in Profitability Analysis .
12. Choose until the overview tree appears.
13. In the dialog box, choose Yes.
138 April 2001
SAP AG Customer Service (CS)
Service Processing and Resource-Related Billing with a Service Contract
Service Processing and Resource-Related Billing with a Service Contract
Purpose
This process shows you how to create and process a service order for repair or maintenance work at a customer device for which a service contract was completed. It incorporates the confirmation of the service order and resource-related billing with reference to the service contract.
Prerequisites
The customer calls to report an equipment breakdown. A service technician must replace the damaged parts in the equipment. A service contract exists for this equipment. The contract incorporates special price agreements for the materials to be used during the repair work. You create a service order, and the system displays the contract for the damaged equipment on the object information screen. The components required for the repair work are assigned to the individual operations in the order. The cost report gives you an overview of the planned costs determined for the order as a result. The actual hours worked by the service technician as well as the components replaced are confirmed for the service order. The system creates a billing request for resource-related billing. In doing this, the system takes price determination information from the service contract including any additional price agreements into account. The billing request is processed in the Sales and Distribution application component and released for billing.
This process can also be executed in conjunction with the process Processing a Service Contract with Periodic Billing instead of the prepared contract and equipment number specified. This enables you to use the contract and equipment number you have created.
Process Flow
You can find the data for this process under .
1. Creating a Service Order from a Notification
2. Assigning Components and Releasing a Service Order
3. Posting Goods Issues for a Service Order
6. Creating a Billing Document from a Billing Request
7. Settling the Costs of the Service Order to the Service Contract
April 2001 139
Customer Service (CS) SAP AG
Data Used During This Process
Data Used During This Process
Field
Data
Plant
1200
Service order type
SM01
Equipment
10003552
Service contract
40000073
Billing request
LV
Sold-to party
1032
Materials
R-1120 R-1111
Sales organization
1000
Distribution channel
14
Division
00
Maintenance planning plant
1200
Maintenance plant
1200
Business area
8000
140 April 2001
SAP AG Customer Service (CS)
Creating a Service Order from a Notification
Creating a Service Order from a Notification
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Notification → Create (Special) → Problem Notification
Transaction Code
IW54, VA43
2. Enter the following data:
Field
Data
Equipment
10003552 or equipment number generated in the scenario Processing a Service Contract with Periodic Billing
3. Choose the Contact person address tab page.
4. Enter the following data:
Field
Data
Description (notification)
CPU defective (in the first row)
Contact person
Contact person (using the input help)
Priority
High
You access the list of contact persons by positioning your cursor in the second entry field of the Contact person line and choosing the input help.
5. In the dialog box, position your cursor on a contact person, then choose .
6. Choose .
7. To check the object information, select in the Reference object screen area.
The Object information dialog box appears. You can check both existing notifications and contract data.
8. To view the detailed data for the order, choose in the Contract screen area.
9. To display the items and rules of the billing plan, select your service item and choose Bill. Plan.
10. Choose .
11. Choose Pricing agrt.
12. Check the following entries:
Field
Data
Material
R-1111
Amount
15
Unit per unit of measure
%
April 2001 141
Customer Service (CS) SAP AG
Creating a Service Order from a Notification
Material
R-1120
Amount
10
Unit
%
13. Choose twice.
If your contract contains configurable or configured service materials, you will also see the Configuration icon in the dialog box in the Contract screen area.
14. To display the characteristic value assignments, choose if it appears on your screen.
15. To leave the dialog box with the characteristic values, choose .
16. Choose .
17. To generate tasks immediately for your notification that are based on the contract configuration, choose Edit → Tasks → Determine.
The system displays the message 2 tasks were created from the response profile.
18. Choose the Tasks tab page.
You see a list of tasks that the system has created for your notification.
19. To check the planned start and finish date for each task, select the first task, then choose .
The system calculates this data from the response and service profiles that were defined in PM Customizing. If the service contract contains a configurable service with a response profile and a service profile, both profiles are determined with the help of the assigned characteristic values. If not, the system proposes the values as a default based on the notification category.
20. Choose Close, then choose the Notification tab page.
21. To create a service order from the service notification, choose in the order line.
22. Choose .
23. Check the following entries:
Field
Data
Description
CPU defective
Mn.wk.ctr
PC-SERVS/1200
WkCtr/Plnt
PC-SERVS/1200
Work durtn
2 24. Choose .
25. Choose and note the number of your service order.
26. Choose until the overview tree appears. 142 April 2001
SAP AG Customer Service (CS)
Creating a Service Order from a Notification
27. In the dialog box, choose No.
April 2001 143
Customer Service (CS) SAP AG
Assigning Components and Releasing a Service Order
Assigning Components and Releasing a Service Order
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Order → Service Order → Change
Transaction Code
IW32
2. Enter the following data:
Field
Data
Order
Number of your service order
3. Choose .
4. Choose the Components tab page.
5. Choose List.
6. Select the items R-1111 and R-1120, then choose .
7. Choose .
8. Enter the following data:
Field
Data
Order
Number of your service order (is proposed by the system per default)
9. Choose Costs.
The system displays the planned costs for the order.
10. Choose the Header data tab page.
11. To release the order, choose .
12. In the dialog box, select W/o print, then choose .
13. Choose until the overview tree appears.
144 April 2001
SAP AG Customer Service (CS)
Posting Goods Issues for a Service Order
Posting Goods Issues for a Service Order
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Confirmation → Goods Movement → Goods Movement
Transaction Code
MB11
2. Choose To order.
3. In the dialog box, enter the following data:
Field
Data
Order
Number of your service order
4. Choose .
5. If necessary, enter the following data:
Field
Data
SLoc (first item)
0001
SLoc (second item)
0001
6. Select the items you want to post, then choose Goods movement → Post.
7. Choose until the overview tree appears.
8. In the dialog box, choose Yes.
April 2001 145
Customer Service (CS) SAP AG
Confirming a Service Order
Confirming a Service Order
9. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Confirmation → Entry → Individual Confirmation (Time)
Transaction Code
IW41
10. Enter the following data:
Field
Data
Order
Number of your service order
11. Choose .
12. Enter the following data:
Field
Data
Actual work
3
Work start
Today's date
Work end
Today's date 13. Choose .
14. Choose until the overview tree appears.
146 April 2001
SAP AG Customer Service (CS)
Creating a Billing Request
Creating a Billing Request
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Order → Service Order → Display
Transaction Code
IW33
2. Enter the following data:
Field
Data
Order
Number of your service order
3. Choose Costs.
Compare the actual costs with the planned costs for labor and materials for this service order on this screen.
4. Choose until the overview tree appears.
5. Call up the transaction as follows:
Menu Path
From the Completion node, choose Billing Request → Process Individually
Transaction Code
DP90, VA02
6. Enter the following data:
Field
Data
Order
Number of your service order
7. Choose Expenses.
The service order costs incurred due to the material consumption and the repair hours are listed. The costs incurred due to the material consumption are displayed under each respective material number.
8. Choose Sales price.
9. Position the cursor on the billing request row (Deb.Memo Req. F. Ctrct), and choose .
The system displays the billing request items that are generated when you save on the second level. The expenses and value (column Net value) with which the expenses are billed are compared with one another.
10. To call up price determination, double-click on the row for material R-1111 (CPU) that is displayed in the lower screen title.
The costs have been copied to the conditions EK01 (actual costs). The material has a price (condition type PR00) with which it is invoiced. The discount agreed upon in the contract (condition type ZZDC) is granted.
11. To call up price determination, double-click on the row for material R-1120 (Cable 220/235 V) that is displayed in the lower screen title. April 2001 147
Customer Service (CS) SAP AG
Creating a Billing Request
The costs have been copied to the conditions EK01 (actual costs). The material has a price (condition type PR00) with which it is invoiced. The discount agreed upon in the contract (condition type ZZDC) is granted.
12. To call up price determination, double-click on the row for material SM-REPHOUR (Repair Hour) that is displayed in the lower screen title.
The costs have been copied to the conditions EK01 (actual costs). The material has a price (condition type PR00) with which it is invoiced.
13. Choose Billing request.
14. Choose Yes.
The billing request created by the system is automatically displayed due to a default setting.
15. The billing request is initially blocked for billing. To delete the billing block, enter the following data:
Field
Data
Billing block
Delete existing block 16. Choose .
17. Note the number of the billing request.
18. Choose until the overview tree appears.
148 April 2001
SAP AG Customer Service (CS)
Creating a Billing Document from a Billing Request
Creating a Billing Document from a Billing Request
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Completion → Billing Document → Create
Transaction Code
VF01
2. Enter the following data:
Field
Data
Document
Number of the billing request 3. Choose .
The system displays an overview of the billing items.
4. Choose .
5. Choose until the overview tree appears.
April 2001 149
Customer Service (CS) SAP AG
Settling the Costs of the Service Order to the Service Contract
Settling the Costs of the Service Order to the Service Contract
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Order → Service Order → Display
Transaction Code
IW33
2. Enter the following data:
Field
Data
Order
Number of your service order
3. Choose .
4. Choose Extras → Cost reports → Planned/actual comparison.
On the Order cost element display: Selection screen, you can check the personnel and material costs for your service order.
5. Choose .
6. Choose until the overview tree appears.
7. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Agreements → Contracts → Contract → Display
Transaction Code
VA43
8. Enter the following data:
Field
Data
Contract
40000073 or the contract number generated in the scenario Processing a Service Contract with Periodic Billing
9. Choose .
10. To display the actual revenues for your service contract, choose Environment → Cost report.
11. Choose until the overview tree appears.
12. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Completion → Order Settlement → Settle Individually
Transaction Code
KO88
13. If the Set controlling area dialog box appears, enter the following data, then choose :
Field
Data 150 April 2001
SAP AG Customer Service (CS)
Settling the Costs of the Service Order to the Service Contract
Controlling area
1000
14. Enter the following data:
Field
Data
Order
Number of your service order
Settlement period
Current period
Fiscal year
Current fiscal year
Test run
Deselect
15. Choose .
16. Choose until the overview tree appears.
17. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Order → Service Order → Display
Transaction Code
IW33
18. Enter the following data:
Field
Data
Order
Number of your service order
19. Choose .
20. Choose Extras → Cost reports → Planned/actual comparison.
21. Check whether all actual costs for your order have been settled.
22. Choose until the overview tree appears.
23. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Agreements → Contracts → Contract → Display
Transaction Code
VA43
24. Enter the following data:
Field
Europe
Contract
40000073 or the contract number generated in the scenario Processing a Service Contract with Periodic Billing
25. Choose .
26. Choose Environment → Cost report, then check whether the costs for materials and wages for your service order are now displayed in addition to the revenues.
27. Choose until the overview tree appears.
28. In the dialog box, choose Yes.
April 2001 151
Customer Service (CS) SAP AG
Settling the Costs of the Service Order to the Service Contract
If you have not performed this scenario in isolation, but together with the process Processing a Service Contract with Periodic Billing , you can continue processing your service order by choosing the following process: Performing Periodic Billing .
152 April 2001
SAP AG Customer Service (CS)
Spare Parts Delivery with a Service Contract
Spare Parts Delivery with a Service Contract
Purpose
The customer requests spare parts for a piece of equipment. A service contract applies to this equipment. The contract states that a price reduction is to be given when spare parts are delivered.
The logistical structure of this process is identical to that of the process Service Management - Spare Parts Delivery . In the environment of the IDES processes for service contracts, we also describe here the transfer of price agreements from a service contract to a spare parts order. We show the function for condition exclusion. You can use the condition exclusion to specify that given price agreements are to be used alternately, and therefore cannot be transferred together in one order item.
You can find more information about this process under .
Process Flow
You can find the data for this process under .
1. Creating a Service Notification and a Spare Parts Order
2. Creating a Spare Parts Order
3. Creating a Billing Document
April 2001 153
Customer Service (CS) SAP AG
Additional Process Information
Additional Process Information
The following additional information is aimed at IDES users with prior knowledge of Customizing for Pricing.
Condition Exclusion
Two exclusion groups (SM01 and SM02) have been defined for the condition exclusion described in this process. The first group SM01 contains condition type ZZDC. Condition type ZZWV is assigned to the group SM02. Pricing for sales document type ZERS (spare parts order) is determined through pricing procedure ZSM001 The pricing of this pricing procedure uses an exclusive exclusion method for the two groups. With this method, all condition types contained in the second group are set to inactive if a condition type of the first group exists in the document.
154 April 2001
SAP AG Customer Service (CS)
Data Used During This Process
Data Used During This Process
Field
Data
Description
Warehouse number
012
Warehouse Dresden
Plant
1200
Dresden
Material number
R-1130
Spare part
Material number
R-1160
Spare part
Sales organization
1000
Sales organization Germany
Distribution channel 14
Service
Division
00
Cross-divisional division
Sold-to party
1172
Customer
Equipment
10003592
Equipment
April 2001 155
Customer Service (CS) SAP AG
Creating a Service Notification and a Spare Parts Order
Creating a Service Notification and a Spare Parts Order
12. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Notification → Create (Special) → Problem Notification
Transaction Code
IW54
13. Enter the following data:
Field
Data
Equipment
10003592 14. Choose .
15. Choose the Contact person address tab page.
16. Enter the following data:
Field
Data
Description (notification)
Spare parts request
Contact person
Select a contact person using the F4 help
To call up the list of contact persons, position your cursor in the second entry field of the Contact person line, then choosing the F4 input help.
In the dialog box, position your cursor on a contact person and choose .
17. Choose .
18. To check the object information for your equipment, in the Reference object section, choose .
The Object information dialog box appears.
19. In the Obj. Display section, choose .
The system displays information about spare parts that you can use for your object.
20. Choose .
In the box, you can see that in the Contract block there is a contract for the reference object of the notification.
21. Choose .
22. Choose Service notification → Create sales order → Standard.
23. Enter the following data:
Field
Data
Purch. order number
CB-334455
Material (1st line)
R-1130
156 April 2001
SAP AG Customer Service (CS)
Creating a Service Notification and a Spare Parts Order
Order quantity (1st line)
1
Material (2nd line)
R-1160
Order quantity (2nd line)
1
24. Choose .
25. Choose .
26. Choose .
You see the additional data for material R-1130. The spare part discount (condition type ZZWV) was transferred from the service contract.
27. Choose .
You see the additional data for material R-1160. The pricing has transferred the contract-specific discount for material R-1160 into the item. As the material belongs to the group of spare parts, the general spare part discount (condition type ZZWV) was transferred from the contract. Pricing, however, is customized so that the material-dependent discount excludes the general spare part discount and is therefore deactivated (see the total in the Discount amount line).
28. Select the line for condition type ZZWV and choose .
You can see that the condition has not been activated.
29. Choose twice.
30. Choose the Shipping tab page and note the material availability date.
31. Choose .
32. Choose .
The sales order is also saved in the background.
33. Note the displayed numbers of the service notification and the sales order.
34. Choose until the overview tree appears.
35. In the dialog box, choose No.
April 2001 157
Customer Service (CS) SAP AG
Creating a Spare Parts Order
Creating a Spare Parts Order
10. Call up the transaction as follows:
Menu Path
Logistics → Sales and Distribution → Shipping and Transportation → Outbound Delivery → Create → Single Document → With Reference to Sales Order
Transaction Code
VL01N, LT03
11. Enter the following data:
Field
Data
Shipping point
1200
Selection date
Material availability date
Order
Number of your order
From item
No entry required
To item
No entry required
12. Choose .
13. Choose Subsequent functions → Create transfer order.
14. In the dialog box, choose Yes.
15. Enter the following data:
Field
Data
Warehouse number
012
Plant
1200
Delivery
Proposed by the system
Foreground/background
Background
Adopt pick. quantity
2
16. Choose .
The system creates a transfer order for picking the delivery quantity. The option 2 (Adopt picking quantity) means that the goods issue is posted immediately for that delivery.
17. Note down your delivery number.
18. Choose until the overview tree appears.
158 April 2001
SAP AG Customer Service (CS)
Creating the Billing Document
Creating the Billing Document
36. Call up the transaction as follows:
Menu Path
Logistics → Sales and Distribution → Billing → Billing Document → Create
Transaction Code
VF01
37. Enter the following data:
Field
Data
Document
Your delivery number
38. To display the overview of the billing items, choose .
39. Choose .
The system posts the corresponding accounting documents in the background.
40. Choose until the overview tree appears.
April 2001 159
Customer Service (CS) SAP AG
Controlling
Controlling
160 April 2001
SAP AG Customer Service (CS)
April 2001 161
Customer Service (CS) SAP AG
Controlling for Services
Controlling for Services
Purpose
Controlling for services occurs at two levels in IDES.
A) Controlling at the level of individual service orders and contracts
At this level, you can examine the IDES processes relating to service orders and contracts that use a report to display the costs and revenues for an individual controlling object.
For more information, see the following processes:
Processing a Service Order and Billing
Processing Service Contracts with Periodic Billing
B) Controlling aggregated values in Profitability Analysis
This IDES process deals with this controlling level.
The following overview portrays the flow of costs and revenue for service orders and contracts into Profitability Analysis:
Costs
Revenues
Settlement to Profitability Analysis
Service order without SD documents
When the order is confirmed, the costs are assigned to it
When the order is billed, the revenue is assigned to it
Settlement object = service order
Costs and revenue from the order
Service contract
When the contract is billed periodically, the revenue is assigned to it
Settlement object = service contract
Revenue from the contract
Service order
with reference to
Service contract
When the order is confirmed, the costs are assigned to it
When the order is settled, the order costs are assigned to the contract
When the order is billed, the revenue is assigned to the contract
When the contract is billed periodically, the revenue is assigned to it
Settlement object =
Service contracts
Costs and revenue from the order
Revenue from the contract
You can find more information about this process under .
Process Flow
You can find the data for this process under .
1. Displaying a CS Report in Profitability Analysis
162 April 2001
SAP AG Customer Service (CS)
Controlling for Services
April 2001 163
Customer Service (CS) SAP AG
Additional Process Information
Additional Process Information
Data Basis
In the IDES processes for Customer Service, values are transferred to Profitability Analysis via:
A) Service Order
Costs and revenues of a service order without reference to a contract are posted to Profitability Analysis when the contract is settled.
B) Service Contract
The revenues arising from the billing of the contract are posted to the contract. The revenues arising from the billing of a service order with reference to a contract are also posted to the controlling object "Contract". When you settle the service order, the order costs are posted to the contract. Once the service contract has been settled, the costs and revenues are posted to Profitability Analysis.
If you have not yet run the IDES processes for Customer Service in your system, the values from contract settlement still appear in Profitability Analysis. This is because the IDES contracts are automatically billed and settled periodically.
C) Spare Part Order
When you bill a spare parts order, the values are transferred to Profitability Analysis. The costs of the products are not billed to the individual sales order. Instead, the costs and revenues are compared on an aggregated level for each profitability segment.
164 April 2001
SAP AG Customer Service (CS)
Data Used During This Process
Data Used During This Process
Field
Data
Description
Operating concern
IDEA
Global IDES
Type of CO-PA
Costing-based
Report
IDES-090
Profitability Reports
Sales organization 1000 Frankfurt, Germany
Distribution channel
14
Service
April 2001 165
Customer Service (CS) SAP AG
Displaying a CS Report in Profitability Analysis
Displaying a CS Report in Profitability Analysis
Use
The report IDES-090 Reporting Service Management uses different accounts receivable and service products to demonstrate how the reporting procedure for service management can be structured. The revenues and costs produced in service management have been made compatible with reporting and also analyzed in the form of key figures.
Procedure
1. Call up the transaction as follows:
Menu Path
Accounting → Controlling → Profitability Analysis → Information System → Execute Report
Transaction Code
KE30
If you are calling up a profitability analysis transaction for the first time since logging on to the system, you may be requested to enter the operating concern. If the Set Operating Concern dialog box appears, enter the following data:
Field
Data
Operating concern IDEA
Type of CO-PA Costing-based
2. Choose .
3. Select the IDES-090 report and choose .
4. Enter the following data:
Field Data
Fiscal year
Current fiscal year
From Period
1
Current Period To Period
5. Choose .
The report data is selected again.
You arrive at the basic screen of the report. In the report header, you see the dimensions defined for this report. Sales organization 1000, Germany, Frankfurt and distribution channel 14 Service.
Beneath the report header, you find the navigation field which enables you to navigate through the individual service products. In the form of key figures, you find revenues, sales deductions, costs and the resultant contribution margins, which are displayed in the additional columns and are cumulated for the individual accounts receivable.
6. To access the product level, choose Product in the Navigation area.
166 April 2001
SAP AG Customer Service (CS)
Displaying a CS Report in Profitability Analysis
7. If the Drilldown: Callup Documentation on Hotspots screen appears, choose .
8. Next to the Product field, choose .
9. Select any product for which you would like to analyze the key figures for all customers and choose .
10. In the Navigation area, choose .
The characteristic "Product" now appears in a different color.
11. To access the drilldown list, choose Product.
For each individual key figure, you obtain an overview of all products in sales organization 1000 and distribution channel 14 and of the customers who have generated revenues or costs for these products. It is now possible to perform a direct comparison of all service products. The overall result is displayed in the last line.
12. To view other key figures for this list, choose .
13. Remain on this screen.
April 2001 167
Customer Service (CS) SAP AG
Displaying Line Items
Displaying Line Items
1. Click on the icon to the left of the row for product PC_Service_CONF.
The system highlights the selected row.
2. Choose Goto → Line Items.
3. In the dialog box, choose .
You now see a list of the settlement items. The system displays selected detail information for each item, such as, Posting date or Entered by.
4. Double click on one of the line items.
You now see, for example, the customer name and the organizational units.
You also see the product number and the corresponding assignments to plant- and profit-center level.
Here you can see all the characteristics that can be analyzed in Profitability Analysis. The values for these characteristics were derived from the customer and material master records, the SD partner roles (such as the sales representative), or from CO-PA-specific characteristics.
5. Choose the Value fields tab page.
You can see detailed information about the billed quantity, revenue, discounts and product cost information that were derived from SD and CO-PC. Note that the list of value fields spans several screens.
6. To scroll through the value field screens, choose .
7. Choose until the overview tree appears.
For more information about navigating within a report, see Performing Defined Reports in Profitability Analysis 9 .
168 April 2001
SAP AG Customer Service (CS)
Executing an Existing Report in Profitability Analysis and Getting to Know Reporting Functions
Executing an Existing Report in Profitability Analysis and Getting to Know Reporting Functions
Purpose
This script demonstrates how to execute a predefined report and manipulate the report data using various interactive reporting features. This script also demonstrates how to link several reports via the report-report interface and perform contribution margin analysis.
You can find further information about reporting under Creating a Basic Report in Profitability Analysis and Creating Forms and Reports in Profitability Analysis .
Prerequisites
Before you start, the parameters in your user profile must be defined. This is done in Setting Up Parameters in Your User Profile .
You can find more information about this process under .
Process Flow
You can find the data for this process under .
Selecting a Report in CO-PA 1.
2.
Drilling Down to the Lowest Level (Including Line Item Detail)
Line Item Analysis (Including Integration with MM and SD) 7 3.
5.
Changing the Report Currency 4 7.
8. Displaying and Creating Exceptions
April 2001 169
Customer Service (CS) SAP AG
Additional Process Information
Additional Process Information
Profitability analysis allows you to evaluate user-definable profitability segments (such as products, customers, product lines, regions, business areas etc). The aim of the profitability analysis system is to provide your sales, management board, and corporate planning departments with information to support internal accounting and decision making. Based on the profitability segments that you choose for your organization, profitability analysis allows you to create your own tailor-made reports to analyze gross contribution or other operating figures (per profitability segment or a combination of profitability segments).
170 April 2001
SAP AG Customer Service (CS)
Data Used During This Process
Data Used During This Process
Field
Data
Operating concern
IDEA
Type of Prof. analysis
Costing-based
Report
IDES-020
Sales organization
3000
Fiscal year
1996
Period from
001
08
Plan version 100
Line item layout
IDES-04
Report IDES-030
Period to
April 2001 171
Customer Service (CS) SAP AG
Setting Up Parameters in Your User Profile
Setting Up Parameters in Your User Profile
1. Call up the transaction as follows:
Menu Path
System → User profile → Own data
Transaction Code
SU3
2. Choose the Parameters tab page.
3. Enter the following data:
Field
Data
Description
Parameters
BEV
Parameter ID for report line structure
Value
D1
Default report line structure
Parameters
ERB
Parameter ID for operating concern
Value
IDEA
Default operating concern
4. Save your entries.
Once you have defined these parameters, the system will display them automatically as default entries when an entry for the corresponding field is required.
172 April 2001
SAP AG Customer Service (CS)
Selecting a Report in CO-PA
Selecting a Report in CO-PA
1. Call up the transaction as follows:
Menu Path
Accounting → Controlling → Profitability Analysis → Information System → Execute Report
Transaction Code
KE30
If you are performing a profitability analysis transaction for the first time since logging on, the system displays the Set Operating Concern dialog box.
2. Enter the following data:
Field Data
Operating concern
IDEA
Costing-based
select
3. Choose .
This dialog box will appear only once during your session. After you make the selection, the system will automatically select the respective operating concern and type of profitability analysis.
4. Select report IDES-020.
5. Choose .
6. Enter the following data:
Field
Data
Sales org. 1000
From Fiscal Year 2000
From Period 1
To Period
12
7. Choose .
The system displays the report list - an analysis of divisions according to cumulative actual, cumulative plan, and % variance.
8. Remain on the Execute Profitability Report Plan/act./var. cum screen.
April 2001 173
Customer Service (CS) SAP AG
174 April 2001
SAP AG Customer Service (CS)
Drilling Down to the Lowest Level (Including Line Item Detail)
Drilling Down to the Lowest Level (Including Line Item Detail)
Use
A profitability analysis report can contain multiple levels of detail (profitability segments). The CO-PA reporting tool provides you with easy-to-use functions for navigating through the data. For example, you can move from one profitability segment to the next, deactivate a level, switch between an overview and a detail report, or display the origins of the data.
At the top of the screen, you see the company logo (IDES), which every organization can define and include in reports.
In the Navigation area (first area in the middle of the screen), you see the characteristics that were selected in the report definition. The second area in the middle of the screen displays the values for these characteristics.
At the bottom left of the screen, you see the detailed list, which displays the detailed key figures for a characteristic combination.
At the bottom right of the screen, you see the graphical display of the characteristic values. All of this display is set in report definition, see Output type.
You can set the size of individual the screen areas by using the left mouse button to
move the vertical and horizontal screen bars.
1. In the second area in the middle of the screen, double-click the 01 Pumps division.
Procedure
2. Double-click the distribution channel 10, Final customer sales.
You see the material groups.
To see the characteristic values, you can select the characteristic in the Navigation area and move it to the second area on the right side using drag and drop.
3. Move the characteristic ProdHier01-1 to the second area using drag and drop.
Material Group and ProdHier change places.
4. In the Navigation area, position your cursor on the division 01 and press the right mouse button.
5. In the menu, choose Choose Characteristic Value.
6. Double-click 04 Lighting.
The characteristic values have been adjusted to suit the characteristics displayed. Hence you see distribution channel 12 (and no longer 10) because 12 is relevant for sales in division Lighting; the product hierarchy has also been changed.
7. In the second area, double-click Lighting.
April 2001 175
Customer Service (CS) SAP AG
Drilling Down to the Lowest Level (Including Line Item Detail)
The system displays the product hierarchy 2.
8. Double-click bulbs .
9. Position your cursor on the graphic, then press the right mouse button.
You can change the formatting individually.
10. In the division Cumulated Actual data;1-Sales quantity, select the row containing the value for the product L-40C.
The cell is highlighted.
11. Choose Goto → Line Items.
The system displays a warning indicating that your selection is not very specific and that it could take a while to read the line items. This is because you selected a column that spans multiple periods.
12. Choose .
The system takes you to the Display Actual Line Items: List screen. A list of all the billing line items is displayed. Selected information (e.g. posting date, user id) is displayed for each line item.
The fields that are displayed are defined in a layout. In addition to the standard layout which you are currently displaying, you can also define additional custom layouts. These layouts can contain any information available on the CO-PA line item, including all the profitability segments and value fields.
You now change the layout of the line item list.
13. Choose Extras → Change line item layout... .
14. Select IDES-04 Cust./Mat.Values, then choose .
Note that the same line items are displayed, but with different information for each line item, such as the customer and product number and selected value fields.
15. Double-click any document number.
The line item detail is displayed.
16. Remain on this screen.
176 April 2001
SAP AG Customer Service (CS)
April 2001 177
Customer Service (CS) SAP AG
178 April 2001
SAP AG Customer Service (CS)
Line Item Analysis (Including Integration with MM and SD)
Line Item Analysis (Including Integration with MM and SD)
1. On the Characteristics tab page, note the detailed information of the position that is
displayed.
The characteristics represent all the dimensions that you can use to analyze your CO-PA data. They are derived either from the customer and material master and SD partner roles (such as sales employee) or from other characteristics.
2. Choose the Value Fields tab page.
This tab page provides detailed information on order and invoice quantities, revenues, sales deductions, and detailed product cost components.
3. Choose Environment → Integration.
A dialog box asks you which amount you would like to display.
4. Select Display Sales Order, then choose .
5. Select the sales order item 10, then choose Environment → Display document flow.
The system displays the complete flow of business events that have occurred.
Note that, using reporting, you have just drilled down from a summary analysis from the industry to a single billing document (CO-PA line item), and from there to the original sales order. This shows the quality of information available from an integrated system.
6. Choose until the Execute Profitability Report Plan/act/var. cum screen appears.
The detailed product list appears.
7. Remain on this screen.
April 2001 179
Customer Service (CS) SAP AG
180 April 2001
SAP AG Customer Service (CS)
Report-Report Interface
Report-Report Interface
Use
On the Execute Profitability Report Plan/act. var. cum screen, the first section of the lowest screen area shows you a detailed analysis of the contribution margin for the product, revenue, and discount, as well as detailed product cost data.
You can display every level of the contribution margin schema (for example, data is summarized at division level)
The following procedure is based on the assumption that you are not happy with the products contribution margin 3 in % (first column, last report row).
Using the report-report interface, you call up a test report to ascertain how you can increase the contribution margin for this product.
Procedure
1. Select the product LC-40C.
2. Choose .
3. On the Selection: Contribution Margin Analysis screen, leave the default value of 20% as well as the other defaults unchanged and select .
The system displays the simulation report. In the first column, you can see actual data. Note that the margin % is less than 20%. The second column displays plan data. In the third column, the system simulates a margin of 20%. The system calculates by how much the variable and fixed manufacturing costs and the overhead surcharges would have to be reduced to increase the margin. The assumption is that the variable and fixed manufacturing costs and the overhead surcharges would be reduced in proportion to the actual costs.
4. Choose .
5. In the dialog box, choose Yes.
The original report appears.
6. Remain on this screen.
April 2001 181
Customer Service (CS) SAP AG
Displaying Attributes
Displaying Attributes
Use
A report of display attributes can be displayed in a separate dialog box or in the lead column. You can only display attributes for characteristics that have a single specified value. You can not display attributes for intervals or selection options.
Procedure
1. Position the cursor on the product L-40C, then choose Attributes.
The size and the dimensions of the selected product are displayed in the dialog box.
2. To return to the Execute Profitability Report Plan/act./var. cum. screen, choose .
3. To display the master data of a material, position the cursor on L-40C, then choose Goto → Display Master Data.
You are now in the Material Ledger application, where you can analyze master data in greater detail.
4. Choose to return to the report.
182 April 2001
SAP AG Customer Service (CS)
Hit Lists
Hit Lists
1. On the Execute Profitability Report Plan/act/var. cum screen, select the heading of the Cumulated act. column (in the sorted list).
The column is selected and highlighted.
2. Choose Edit → Ranking list → Top N.
3. Enter the following data:
Field Data
First ones only
3
4. Choose .
The system displays the top 3 products individually. The aggregated total of these 3 products and the rest of the products is displayed at the end of the list.
Similar hit lists can be created for Top %, Last n, and Last %.
5. Choose Settings → Percentage/Absolute.
Instead of absolute values, the system displays the products percentage of total contribution margin (previously display as absolute amounts).
6. To return to the original display, choose Settings → Percentage/Absolute..
7. Deselect the Cumulated Act... column.
8. Remain on this screen.
April 2001 183
Customer Service (CS) SAP AG
Changing the Report Currency
Changing the Report Currency
Use
This procedure shows you how to change the report currency for all report columns.
Procedure
1. Make sure that the cursor is not on a field in a column, otherwise you will change the currency of that column only.
2. Choose .
3. Enter the following data:
Field
Data
Currency
USD
Translation key
Mean rate, cutoff date today
The currency translation type determines the exchange rate to convert to EUR.
4. Choose Execute.
In the column headings, you can see that the amounts are now displayed in the selected currency.
5. Remain on this screen.
184 April 2001
SAP AG Customer Service (CS)
Displaying and Creating Exceptions
Displaying and Creating Exceptions
Use
While analyzing the current report, you may have noticed that some amounts are highlighted in
different colors. This is due to exceptions that were defined for the report.
Do not make any changes to the exception rules defined for this report. Exception rules are not user-specific. Therefore, any changes would affect every user.
Procedure
1. Choose Extras → Exceptions.
2. In the dialog box, choose Display exceptions.
3. Double-click the exception 0000000001.
Note that you can define upper and lower threshold values in the dialog box. In this instance, the exception causes values exceeding the threshold value of 20% to appear in red (as a warning).
4. To return to the report list, choose twice.
5. Choose Report → Exit.
6. In the dialog box, choose Yes.
7. Choose until the overview tree appears.
April 2001 185
Customer Service (CS) SAP AG
186 April 2001
SAP AG Customer Service (CS)
Workflow in Customer Service
Workflow in Customer Service
April 2001 187
Customer Service (CS) SAP AG
Workflow - Service Management
Workflow - Service Management
Purpose
There is a growing trend for companies to provide certain services for other companies, either in conjunction with a specific product that they manufacture, or simply as a main line of business. Consequently, customer expectations of improved after-sales service have risen.
When a machine installed at a customer site breaks down or requires servicing, the customer contact person can either log a call directly in the R/3 System, or contact the customer service department of the equipment supplier or manufacturer by phone, fax or mail, who in turn logs the call in the system.
In this scenario, a call has been received reporting a malfunctioning hard drive on a PC. The PC manufacturer receives the call and resolves the customers problem through its hotline service.
You can find more information about this process under .
Process Flow
You can find the data for this process under .
Logging the Service Notification 1.
2. Processing and Completing the Service Notification 188 April 2001
SAP AG Customer Service (CS)
Additional Process Information
Additional Process Information
Further information about the technical realization of this demo with the SAP Business Workflow tools and the necessary preparations and customizing settings can be found in the SAP Library.
Call up the transaction as follows:
Menu Path
R/3 Basis Library → Business Engineering Workbench → SAP Business Workflow → Application Workflow Scenarios → PM Plant Maintenance and Service Management → Service Management (PM-SMA).
April 2001 189
Customer Service (CS) SAP AG
Data Used During This Process
Data Used During This Process
Field
Data
Description
Workflow User ID
WF-SM-1
Service technician
Equipment
10003594
Personal computer
Damage
EN
Hard disk out of order
Task code
TEL
Call back customer
Person responsible
1527
Alexander Maroto
Sales document
40000076
Service contract
190 April 2001
SAP AG Customer Service (CS)
Logging the Service Notification
Logging the Service Notification
Use
Log on to the IDES system. This user reports the service notification.
Procedure
1. Call up the transaction as follows:
Menu Path
Logistics → Customer Service → Service Processing → Notification → Create (Special) → Problem Notification.
Transaction Code
IW54
2. Enter the following data:
Field
Data
Equipment
10003594 3. Choose .
The system calls up the service contract data (40000076) for this equipment.
The system also informs you that the catalog profile has been copied from the equipment. This means that information related to the equipment, such as contact information, has been included in the service notification.
4. Choose the Items tab page, then position your cursor on the Damage field and choose the F4 input help.
You see a catalog selection.
5. Choose E (Hard disk out of order) and Select in the dialog box.
6. Choose .
Note the notification number.
7. Choose .
8. Choose No in the Confirmation Prompt dialog box.
The Confirm. Prompt dialog box refers to the creation of a new service notification.
9. Log off from this IDES system.
April 2001 191
Customer Service (CS) SAP AG
Processing and Completing the Service Notification
Processing and Completing the Service Notification
Use
The service technician who processed this call has solved the problem by telephone and now records the results.
Procedure
1. Log on to your IDES system as user WF-SM-1, password WELCOME.
2. Call up the transaction as follows:
Menu Path
Office → Workplace → Inbox → Workflow
Transaction Code
SBWP
On the Workflow screen, you see a list of service notifications.
3. Double-click on for your notification number.
4. Choose the Tasks tab page.
5. Position your cursor on the Task code field, then choose the F4 input help.
You see a catalog selection.
6. Choose the "+" character before PC, select the task code TEL and choose Select.
7. Enter the following data:
Field
Data
Responsible
1527 8. Choose .
9. Select the task you have just created.
10. To complete the task, choose .
In the Status field, the status is now TSCO.
11. Choose Service Notification → Functions → Complete.
12. In the Complete dialog box, verify the date and time of the completion of this service notification, then choose .
The system saves the data.
The work item you have processed is no longer displayed, indicating that the work is completed.
13. Choose .
192 April 2001
rewards if it helps
siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.